The lowest level in work breakdown structure contains the:Group of answer choicesactivities.finite elements.atoms.work packages.

Question

The lowest level in work breakdown structure contains the:Group of answer choicesactivities.finite elements.atoms.work packages.

🧐 Not the exact question you are looking for?Go ask a question

Solution

The lowest level in a Work Breakdown Structure (WBS) contains the:

  1. Work Packages: These are the smallest unit of work that a project can be broken down to when creating your WBS. Work packages are the lowest level of a WBS and are used to schedule, cost, monitor and control the project work.

Each work package represents a series of tasks that will be completed by a team or team member. They are typically defined by clear start/end dates, specific required resources, budget, and expected outputs.

So, the correct answer is "work packages".

This problem has been solved

Similar Questions

The lowest level in work breakdown structure contains the:

A typical Statement of work may contain the following, except:Group of answer choicesLocation of workAcceptance CriteriaStatement of workWork breakdown structure

The Work Breakdown Structure (WBS)Group of answer choicesBreaks down the tasks needed to complete the project into the level of detail for accurate calculation of schedule and budgetDescribes the assumptions and constraints associated with the scope of the projectInvolves a sequential breakdown of tasks to be completed for the projectDefines the major tasks needed to complete the project

A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task? A list that identifies the logical way to progress through workTangible and measurable outcome expected from a projectWork performed to complete or manage the deliverables for a projectDiscrete work required to complete parts of a project

Which one of the following is captured in the Work Breakdown Structure (WBS)?The life cycle phasesThe logical order of tasksThe scope of the projectProject costs

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.