A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task? A list that identifies the logical way to progress through workTangible and measurable outcome expected from a projectWork performed to complete or manage the deliverables for a projectDiscrete work required to complete parts of a project
Question
A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task? A list that identifies the logical way to progress through workTangible and measurable outcome expected from a projectWork performed to complete or manage the deliverables for a projectDiscrete work required to complete parts of a project
Solution
A task is described as the discrete work required to complete parts of a project.
Similar Questions
A Work Breakdown Structure (WBS) is a:Group of answer choicesHierarchy of organizational personnelDiagram of cost accounts mapped to their functional organizationsA task- or deliverable-oriented hierarchy of activitiesSchedule of work activities, aligned in a network
The Work Breakdown Structure (WBS)Group of answer choicesBreaks down the tasks needed to complete the project into the level of detail for accurate calculation of schedule and budgetDescribes the assumptions and constraints associated with the scope of the projectInvolves a sequential breakdown of tasks to be completed for the projectDefines the major tasks needed to complete the project
Which one of the following is captured in the Work Breakdown Structure (WBS)?The life cycle phasesThe logical order of tasksThe scope of the projectProject costs
What relationship between work packages and the work breakdown structure (WBS) does the time phased work package budget demonstrate?Multiple choice question.More than one work package can be represented by a WBS activity.All work packages are built on a five week horizon.Work packages only include labor costs, and baseline budgets are only for labor.
In project management, what does the acronym WBS stand for?
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.