Which one of the following is captured in the Work Breakdown Structure (WBS)?The life cycle phasesThe logical order of tasksThe scope of the projectProject costs

Question

Which one of the following is captured in the Work Breakdown Structure (WBS)?The life cycle phasesThe logical order of tasksThe scope of the projectProject costs

🧐 Not the exact question you are looking for?Go ask a question

Solution

The Work Breakdown Structure (WBS) captures the scope of the project. It is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the project, and represents the work specified in the current approved project scope statement.

Similar Questions

The Work Breakdown Structure (WBS)Group of answer choicesBreaks down the tasks needed to complete the project into the level of detail for accurate calculation of schedule and budgetDescribes the assumptions and constraints associated with the scope of the projectInvolves a sequential breakdown of tasks to be completed for the projectDefines the major tasks needed to complete the project

A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task? A list that identifies the logical way to progress through workTangible and measurable outcome expected from a projectWork performed to complete or manage the deliverables for a projectDiscrete work required to complete parts of a project

Which of the following elements is NOT included as part of the five-step process of developing a work breakdown structure?Developing the budgetIdentifying tasksIdentifying deliverablesSequencing the activities

A Work Breakdown Structure (WBS) is a:Group of answer choicesHierarchy of organizational personnelDiagram of cost accounts mapped to their functional organizationsA task- or deliverable-oriented hierarchy of activitiesSchedule of work activities, aligned in a network

Which of the following components of a project plan is completed first? Work breakdown structureRisk management planProject budgetProject schedule

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.