The Work Breakdown Structure (WBS)Group of answer choicesBreaks down the tasks needed to complete the project into the level of detail for accurate calculation of schedule and budgetDescribes the assumptions and constraints associated with the scope of the projectInvolves a sequential breakdown of tasks to be completed for the projectDefines the major tasks needed to complete the project
Question
The Work Breakdown Structure (WBS)Group of answer choicesBreaks down the tasks needed to complete the project into the level of detail for accurate calculation of schedule and budgetDescribes the assumptions and constraints associated with the scope of the projectInvolves a sequential breakdown of tasks to be completed for the projectDefines the major tasks needed to complete the project
Solution
The Work Breakdown Structure (WBS) breaks down the tasks needed to complete the project into the level of detail for accurate calculation of schedule and budget. This is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
Here are the steps to create a WBS:
- Identify the main deliverables for the project.
- Break down the main deliverables into smaller, more manageable tasks.
- Continue to break down these tasks until they are manageable and can be accurately estimated for cost and duration.
- Assign a unique identifier to each task in the WBS for easier tracking.
- Verify the accuracy of the WBS by reviewing it with the project team and stakeholders.
The WBS does not describe the assumptions and constraints associated with the scope of the project, nor does it involve a sequential breakdown of tasks to be completed for the project. It simply defines the major tasks needed to complete the project.
Similar Questions
Which one of the following is captured in the Work Breakdown Structure (WBS)?The life cycle phasesThe logical order of tasksThe scope of the projectProject costs
A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task? A list that identifies the logical way to progress through workTangible and measurable outcome expected from a projectWork performed to complete or manage the deliverables for a projectDiscrete work required to complete parts of a project
A Work Breakdown Structure (WBS) is a:Group of answer choicesHierarchy of organizational personnelDiagram of cost accounts mapped to their functional organizationsA task- or deliverable-oriented hierarchy of activitiesSchedule of work activities, aligned in a network
What relationship between work packages and the work breakdown structure (WBS) does the time phased work package budget demonstrate?Multiple choice question.More than one work package can be represented by a WBS activity.All work packages are built on a five week horizon.Work packages only include labor costs, and baseline budgets are only for labor.
Apa yang dimaksud dengan WBS (Work Breakdown Structure)?Question 34Answera.Work Breakdown Scheduleb.World Business Systemc.Work Breakdown Structured.Work Budgeting System
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.