Knowee
Questions
Features
Study Tools

What relationship between work packages and the work breakdown structure (WBS) does the time phased work package budget demonstrate?Multiple choice question.More than one work package can be represented by a WBS activity.All work packages are built on a five week horizon.Work packages only include labor costs, and baseline budgets are only for labor.

Question

What relationship between work packages and the work breakdown structure (WBS) does the time phased work package budget demonstrate?Multiple choice question.More than one work package can be represented by a WBS activity.All work packages are built on a five week horizon.Work packages only include labor costs, and baseline budgets are only for labor.

🧐 Not the exact question you are looking for?Go ask a question

Solution

The time-phased work package budget demonstrates the relationship between work packages and the Work Breakdown Structure (WBS) by showing how the total cost of a project is divided among its various components. This budget is a detailed version of the cost baseline, which includes labor, materials, and overhead costs for each work package over the duration of the project.

So, the correct answer to your multiple-choice question would be: "More than one work package can be represented by a WBS activity." This is because a WBS activity can be broken down into multiple work packages, each with its own budget and timeline. The other options are not accurate as work packages can include more than just labor costs, and there is no rule that all work packages are built on a five-week horizon.

This problem has been solved

Similar Questions

What is a general guide for how to define a WBS work package?Group of answer choicesThe work package represents the tasks that can be completed during an 8-hour day.The work package is a general overview of the project scope.The work package is the level at which costs are usually tracked for senior management and general high-level monitoring. The work package represents a piece of work that can be assigned and monitored.

The Work Breakdown Structure (WBS)Group of answer choicesBreaks down the tasks needed to complete the project into the level of detail for accurate calculation of schedule and budgetDescribes the assumptions and constraints associated with the scope of the projectInvolves a sequential breakdown of tasks to be completed for the projectDefines the major tasks needed to complete the project

A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task? A list that identifies the logical way to progress through workTangible and measurable outcome expected from a projectWork performed to complete or manage the deliverables for a projectDiscrete work required to complete parts of a project

Which one of the following is captured in the Work Breakdown Structure (WBS)?The life cycle phasesThe logical order of tasksThe scope of the projectProject costs

Apa yang dimaksud dengan WBS (Work Breakdown Structure)?Question 34Answera.Work Breakdown Scheduleb.World Business Systemc.Work Breakdown Structured.Work Budgeting System

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.