The lowest level in work breakdown structure contains the:

Question

The lowest level in work breakdown structure contains the:

🧐 Not the exact question you are looking for?Go ask a question

Solution

The lowest level in a Work Breakdown Structure (WBS) contains the Work Packages.

Here's a step-by-step explanation:

  1. The Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.

  2. It organizes and defines the total scope of the project, and represents the work specified in the current approved project scope statement.

  3. The WBS is structured in a hierarchical way. The first level represents the final deliverable or project. Subsequent levels represent the breakdown of the final deliverable into smaller pieces.

  4. These smaller pieces are called work packages and they form the lowest level of the WBS.

  5. Work packages are a group of related tasks that are defined at the same level within the WBS. They provide a logical basis for defining activities and assigning resources.

  6. Each work package represents a series of tasks that will be completed together. Once all the work packages of a higher level element are complete, the work for that element

This problem has been solved

Similar Questions

The lowest level in work breakdown structure contains the:Group of answer choicesactivities.finite elements.atoms.work packages.

Which one of the following is captured in the Work Breakdown Structure (WBS)?The life cycle phasesThe logical order of tasksThe scope of the projectProject costs

A typical Statement of work may contain the following, except:Group of answer choicesLocation of workAcceptance CriteriaStatement of workWork breakdown structure

Which of the following elements is NOT included as part of the five-step process of developing a work breakdown structure?Developing the budgetIdentifying tasksIdentifying deliverablesSequencing the activities

A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task? A list that identifies the logical way to progress through workTangible and measurable outcome expected from a projectWork performed to complete or manage the deliverables for a projectDiscrete work required to complete parts of a project

1/2

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.