Question 8Which of the measures involved in “three-point” time estimations express how long you hope the task will take, assuming everything goes as planned?1 pointMilestone time estimatesPlanning time estimatesOptimistic time estimatesMost likely time estimates
Question
Question 8Which of the measures involved in “three-point” time estimations express how long you hope the task will take, assuming everything goes as planned?1 pointMilestone time estimatesPlanning time estimatesOptimistic time estimatesMost likely time estimates
Solution
The measure involved in "three-point" time estimations that expresses how long you hope the task will take, assuming everything goes as planned, is the Optimistic time estimates.
Similar Questions
Which of the measures involved in “three-point” time estimations is based on how long the task usually takes under normal circumstances, with only slight adjustments to the best-case scenario?1 pointOptimistic time estimatesPessimistic time estimatesMost likely time estimatesPlanning time estimates
You are making time estimates for your project plan. You ask your task expert to estimate how long the task would take if you assume you need to replace your vendor and you experience unexpected turnover right before the task begins. Which of the measures involved in “three-point” time estimations are you asking from your task expert?1 pointMilestone time estimatesPessimistic time estimatesMost likely time estimatesPlanning time estimates
Why is the three-point time estimating technique a good way to determine a confidence rating for your time estimates?1 pointIt is a commonly used technique that everyone is familiar with.It is the time estimating technique that involves input from the most people. It ensures you have considered the best-case and worst-case conditions for a task.It removes all uncertainty from your estimate.10.Question 10
Multiple Choice QuestionPERT uses ____ for each activity.Multiple choice question.three time estimatesfour time estimatesone time estimatetwo time estimates
What type of time estimate considers how long it takes to complete a task, plus the time it takes to test the product?1 pointTimeline estimateEffort estimateConservative estimateTotal duration estimate