You are making time estimates for your project plan. You ask your task expert to estimate how long the task would take if you assume you need to replace your vendor and you experience unexpected turnover right before the task begins. Which of the measures involved in “three-point” time estimations are you asking from your task expert?1 pointMilestone time estimatesPessimistic time estimatesMost likely time estimatesPlanning time estimates

Question

You are making time estimates for your project plan. You ask your task expert to estimate how long the task would take if you assume you need to replace your vendor and you experience unexpected turnover right before the task begins. Which of the measures involved in “three-point” time estimations are you asking from your task expert?1 pointMilestone time estimatesPessimistic time estimatesMost likely time estimatesPlanning time estimates

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

You are asking your task expert for the Pessimistic time estimates. In three-point time estimation, this measure represents the longest time the task might take, considering all the potential risks and challenges, such as replacing a vendor or experiencing unexpected turnover.

Similar Questions

Question 8Which of the measures involved in “three-point” time estimations express how long you hope the task will take, assuming everything goes as planned?1 pointMilestone time estimatesPlanning time estimatesOptimistic time estimatesMost likely time estimates

Which of the measures involved in “three-point” time estimations is based on how long the task usually takes under normal circumstances, with only slight adjustments to the best-case scenario?1 pointOptimistic time estimatesPessimistic time estimatesMost likely time estimatesPlanning time estimates

As a project manager, you try to get an accurate time estimate for a task by communicating with an expert. After receiving their time estimate, you ask questions like, “What equipment do you suppose you’ll have?” and “How many people do you expect to work on the task?” What strategy for getting an accurate time estimate did you choose?1 pointAssess the expert’s confidence level in their estimate.Ask the expert how likely it is that assumptions they have might not work out and how it would affect their estimate.Discuss the assumptions the expert may be making when they give an estimate.Check the expert’s estimates against the actual time spent on similar tasks in previous work.4.Question 4

As a project manager, you identify tasks to complete in a project. Who will you consult to create an accurate time estimate for each task?1 pointA project manager from a different teamThe sponsors of the projectTeam members working on the tasksThe project’s primary stakeholders

What type of time estimate considers how long it takes to complete a task, plus the time it takes to test the product?1 pointTimeline estimateEffort estimateConservative estimateTotal duration estimate