Which of the measures involved in “three-point” time estimations is based on how long the task usually takes under normal circumstances, with only slight adjustments to the best-case scenario?1 pointOptimistic time estimatesPessimistic time estimatesMost likely time estimatesPlanning time estimates

Question

Which of the measures involved in “three-point” time estimations is based on how long the task usually takes under normal circumstances, with only slight adjustments to the best-case scenario?1 pointOptimistic time estimatesPessimistic time estimatesMost likely time estimatesPlanning time estimates

🧐 Not the exact question you are looking for?Go ask a question

Solution

The measure involved in "three-point" time estimations that is based on how long the task usually takes under normal circumstances, with only slight adjustments to the best-case scenario is the "Most likely time estimates".

Similar Questions

Question 8Which of the measures involved in “three-point” time estimations express how long you hope the task will take, assuming everything goes as planned?1 pointMilestone time estimatesPlanning time estimatesOptimistic time estimatesMost likely time estimates

You are making time estimates for your project plan. You ask your task expert to estimate how long the task would take if you assume you need to replace your vendor and you experience unexpected turnover right before the task begins. Which of the measures involved in “three-point” time estimations are you asking from your task expert?1 pointMilestone time estimatesPessimistic time estimatesMost likely time estimatesPlanning time estimates

Why is the three-point time estimating technique a good way to determine a confidence rating for your time estimates?1 pointIt is a commonly used technique that everyone is familiar with.It is the time estimating technique that involves input from the most people. It ensures you have considered the best-case and worst-case conditions for a task.It removes all uncertainty from your estimate.10.Question 10

Which of the following can be highly subjective when monitoring time? Effort estimatesPercentage complete estimatesSchedule estimatesTime estimates

What term refers to a time estimate that only takes into account the actual time it takes to complete a task?1 pointMilestone estimateTaskflow duration estimate Total duration estimateEffort estimate