Multiple Choice QuestionPERT uses ____ for each activity.Multiple choice question.three time estimatesfour time estimatesone time estimatetwo time estimates

Question

Multiple Choice QuestionPERT uses ____ for each activity.Multiple choice question.three time estimatesfour time estimatesone time estimatetwo time estimates

🧐 Not the exact question you are looking for?Go ask a question

Solution

The PERT (Program Evaluation and Review Technique) uses three time estimates for each activity. These estimates are the optimistic time, the most likely time, and the pessimistic time. So, the correct answer is "three time estimates".

Similar Questions

Question 8Which of the measures involved in “three-point” time estimations express how long you hope the task will take, assuming everything goes as planned?1 pointMilestone time estimatesPlanning time estimatesOptimistic time estimatesMost likely time estimates

Which of the measures involved in “three-point” time estimations is based on how long the task usually takes under normal circumstances, with only slight adjustments to the best-case scenario?1 pointOptimistic time estimatesPessimistic time estimatesMost likely time estimatesPlanning time estimates

Multiple Choice QuestionThrough observation and study, a job _____ determines information about a job—the tasks that comprise it and the environment in which it will be performed.Multiple choice question.descriptionreviewspecificationanalysis

Multiple Choice QuestionManagement uses a(n) ______ budget to establish the standard overhead rate.Multiple choice question.masterfixedflexible

3 of 35Progress informationDue in less than 8 hoursDue dateEstimated timeMultiple Choice QuestionMira el dibujo y selecciona la palabra más lógica para completar la frase.  Carmen es __ de Daniel. Multiple choice question.

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.