The Scnrm team of a certain company has identified 40 story points in their new sgftwareproject. Depending on the execution environment they have added 25o/obttffer and onepre-release sprint during the planning stage. Further, they have allocated 2 weel<s timepeg sprint. It has been identified that this tea:n has team velocity value as 14. Find thetotal number of sprints required to execute this software project and time taken tocomplete the project according to the Scmm method

Question

The Scnrm team of a certain company has identified 40 story points in their new sgftwareproject. Depending on the execution environment they have added 25o/obttffer and onepre-release sprint during the planning stage. Further, they have allocated 2 weel<s timepeg sprint. It has been identified that this tea:n has team velocity value as 14. Find thetotal number of sprints required to execute this software project and time taken tocomplete the project according to the Scmm method

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

The Scnrm team of a certain company has identified 40 story points in their new sgftwareproject. Depending on the execution environment they have added 25o/obttffer and onepre-release sprint during the planning stage. Further, they have allocated 2 weel<s timepeg sprint. It has been identified that this tea:n has team velocity value as 14. Find thetotal number of sprints required to execute this software project and time taken tocomplete the project according to the Scmm method.

To find the total number of sprints required to execute the software project, we need to divide the total number of story points by the team velocity value.

Total number of story points: 40 Team velocity value: 14

Number of sprints required = Total number of story points / Team velocity value = 40 / 14 ≈ 2.857

Since we cannot have a fraction of a sprint, we need to round up the number of sprints to the nearest whole number. Therefore, the total number of sprints required to execute the software project is 3.

To calculate the time taken to complete the project, we need to multiply the number of sprints by the duration of each sprint.

Duration of each sprint: 2 weeks

Time taken to complete the project = Number of sprints * Duration of each sprint = 3 * 2 weeks = 6 weeks

According to the Scmm method, the total number of sprints required to execute this software project is 3, and the time taken to complete the project is 6 weeks.

This problem has been solved

Similar Questions

Scrum Estimates

Your team planned to complete 40 story points in each of your previous 3 sprints. However, of the 40 planned within each sprint, your team completed:36 story points in the first sprint28 story points in the second sprint38 story points in the third sprintWhat is your estimated team velocity for the next sprint?Question 5Select one:a.36 story pointsb.34 story pointsc.40 story pointsd.32 story points

What is the measure of the team’s ability to complete work at a certain pace?1 pointCapacity and velocityStory and epicA product roadmapA release plan

Question 4Select the correct statement regarding sprint planning.1 pointThe scrum master describes the goal.The product owner creates new milestones and gives them titles.The development team takes the stories from the top of the product backlog and assigns them to the sprint backlog.The product owner determines the team velocity.

Priority Product Backlog Ltem Relative Size (Sitory PointsI A : Developi ng U ser Managelq^r41ryvlg.qqle 202 B: Developing Server Handlinl3 Module 35J C: Preparing Release Notes 154 D: Executing Test CYcles 205 E: Intesrating PaYment Gatera"a 10It has been appointed a Dev Team with 8 members for this project. In addition to that, it has beenrevealed from the past experience that this team can complete 22 story poinls per sprint'According to the lessons learned from previous similar projects, 20Yo story points are added persprint as the uncertainty buffer. Time allocated per sprint is 2 weeks and cost per month has beenestimated as US$ 2,500.e) Estimate the totalclearly

1/1

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.