Your team planned to complete 40 story points in each of your previous 3 sprints. However, of the 40 planned within each sprint, your team completed:36 story points in the first sprint28 story points in the second sprint38 story points in the third sprintWhat is your estimated team velocity for the next sprint?Question 5Select one:a.36 story pointsb.34 story pointsc.40 story pointsd.32 story points
Question
Your team planned to complete 40 story points in each of your previous 3 sprints. However, of the 40 planned within each sprint, your team completed:36 story points in the first sprint28 story points in the second sprint38 story points in the third sprintWhat is your estimated team velocity for the next sprint?Question 5Select one:a.36 story pointsb.34 story pointsc.40 story pointsd.32 story points
Solution
To calculate the estimated team velocity for the next sprint, you need to find the average of the story points completed in the previous sprints.
Here's how you do it:
-
Add up the total number of story points completed in the previous sprints: 36 (from the first sprint) + 28 (from the second sprint) + 38 (from the third sprint) = 102 story points.
-
Divide the total by the number of sprints to find the average: 102 story points / 3 sprints = 34 story points.
So, the estimated team velocity for the next sprint is 34 story points. Therefore, the answer is b. 34 story points.
Similar Questions
Question 10What is velocity in terms of sprint planning? 1 pointThe speed at which every team should be able to work. A measure of how quickly the team can plan a sprint. Each team has a measure of how quickly they work, for comparison. The number of story points a team can complete in a single sprint.
Which of the following questions does a team’s velocity aim to answer? 1 pointHow long will it take to complete the Product Backlog? What are the team’s opinions on the items to work on? Which team member will take the most points in this Sprint? How many stakeholders does this project need?
Question 4Select the correct statement regarding sprint planning.1 pointThe scrum master describes the goal.The product owner creates new milestones and gives them titles.The development team takes the stories from the top of the product backlog and assigns them to the sprint backlog.The product owner determines the team velocity.
The Scnrm team of a certain company has identified 40 story points in their new sgftwareproject. Depending on the execution environment they have added 25o/obttffer and onepre-release sprint during the planning stage. Further, they have allocated 2 weel<s timepeg sprint. It has been identified that this tea:n has team velocity value as 14. Find thetotal number of sprints required to execute this software project and time taken tocomplete the project according to the Scmm method
Question 4Every sprint should have _____.1 pointseveral iterations through the design, code, test, and deploy cyclecompletion of all items in the backloga three-week durationa clearly stated goal
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.