Priority Product Backlog Ltem Relative Size (Sitory PointsI A : Developi ng U ser Managelq^r41ryvlg.qqle 202 B: Developing Server Handlinl3 Module 35J C: Preparing Release Notes 154 D: Executing Test CYcles 205 E: Intesrating PaYment Gatera"a 10It has been appointed a Dev Team with 8 members for this project. In addition to that, it has beenrevealed from the past experience that this team can complete 22 story poinls per sprint'According to the lessons learned from previous similar projects, 20Yo story points are added persprint as the uncertainty buffer. Time allocated per sprint is 2 weeks and cost per month has beenestimated as US$ 2,500.e) Estimate the totalclearly

Question

Priority Product Backlog Ltem Relative Size (Sitory PointsI A : Developi ng U ser Managelq^r41ryvlg.qqle 202 B: Developing Server Handlinl3 Module 35J C: Preparing Release Notes 154 D: Executing Test CYcles 205 E: Intesrating PaYment Gatera"a 10It has been appointed a Dev Team with 8 members for this project. In addition to that, it has beenrevealed from the past experience that this team can complete 22 story poinls per sprint'According to the lessons learned from previous similar projects, 20Yo story points are added persprint as the uncertainty buffer. Time allocated per sprint is 2 weeks and cost per month has beenestimated as US$ 2,500.e) Estimate the totalclearly

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

To estimate the total effort required for each item in the priority product backlog, we need to calculate the relative size of each item in story points.

A: Developing User Management Module - 202 story points B: Developing Server Handling Module - 35 story points C: Preparing Release Notes - 154 story points D: Executing Test Cycles - 205 story points E: Integrating Payment Gateway - 10 story points

Next, we need to consider the capacity of the development team. The team consists of 8 members, and based on past experience, they can complete 22 story points per sprint.

Since there is uncertainty in the project, we add a buffer of 20% to the story points per sprint. Therefore, the team can complete 22 + (22 * 0.2) = 26.4 story points per sprint.

The time allocated per sprint is 2 weeks, so we can assume there are 2 sprints in a month.

Now, let's calculate the total effort for each item:

A: 202 story points / 26.4 story points per sprint = 7.65 sprints B: 35 story points / 26.4 story points per sprint = 1.33 sprints C: 154 story points / 26.4 story points per sprint = 5.83 sprints D: 205 story points / 26.4 story points per sprint = 7.77 sprints E: 10 story points / 26.4 story points per sprint = 0.38 sprints

Since we have 2 sprints in a month, we can multiply the number of sprints by 2 to get the estimated time in months:

A: 7.65 sprints * 2 = 15.3 months B: 1.33 sprints * 2 = 2.66 months C: 5.83 sprints * 2 = 11.66 months D: 7.77 sprints * 2 = 15.54 months E: 0.38 sprints * 2 = 0.76 months

Finally, let's calculate the estimated cost:

The cost per month is estimated as US$ 2,500.

A: 15.3 months * US2,500=US 2,500 = US 38,250 B: 2.66 months * US2,500=US 2,500 = US 6,650 C: 11.66 months * US2,500=US 2,500 = US 29,150 D: 15.54 months * US2,500=US 2,500 = US 38,850 E: 0.76 months * US2,500=US 2,500 = US 1,900

Therefore, the estimated total effort and cost for each item are as follows:

A: 202 story points, 15.3 months, US38,250B:35storypoints,2.66months,US 38,250 B: 35 story points, 2.66 months, US 6,650 C: 154 story points, 11.66 months, US29,150D:205storypoints,15.54months,US 29,150 D: 205 story points, 15.54 months, US 38,850 E: 10 story points, 0.76 months, US$ 1,900

This problem has been solved

Similar Questions

The product backlog consists of stories _____.1 pointin which stories are refined to be clearer and more directin which epic stories are put first, then in descending order by sizein the order in which they entered the backlog in order of importance and/or business value

Who is responsible for prioritizing the product backlog?I.Product OwnerII.Scrum Team III.StakeholderIV.Scrum Master

The Scnrm team of a certain company has identified 40 story points in their new sgftwareproject. Depending on the execution environment they have added 25o/obttffer and onepre-release sprint during the planning stage. Further, they have allocated 2 weel<s timepeg sprint. It has been identified that this tea:n has team velocity value as 14. Find thetotal number of sprints required to execute this software project and time taken tocomplete the project according to the Scmm method

A Product Owner writing a user story needs the story to fit within the planned Sprint. If the user story is too large, they break it down into multiple scaled-down stories to meet which of the I.N.V.E.S.T. story writing criteria?1 pointIndependentNegotiableValuableSmall

Product backlog should be ordered on the basis of?The complexity of the items being deliveredValue of the items being deliveredBased on the Scrum Team choiceThe risk associated with the items