Product backlog should be ordered on the basis of?The complexity of the items being deliveredValue of the items being deliveredBased on the Scrum Team choiceThe risk associated with the items

Question

Product backlog should be ordered on the basis of?The complexity of the items being deliveredValue of the items being deliveredBased on the Scrum Team choiceThe risk associated with the items

🧐 Not the exact question you are looking for?Go ask a question

Solution

The product backlog should be ordered based on the value of the items being delivered. This is because the main goal of any project is to deliver the highest value to the customer as early as possible.

Here are the steps to order a product backlog:

  1. Identify the Items: The first step is to identify all the items that need to be included in the product backlog. These items could be features, functions, requirements, enhancements, and fixes that need to be developed for the product.

  2. Prioritize the Items: The next step is to prioritize these items. This is usually done by the product owner, who considers factors like the value of the items to the customer, the cost and time required to develop the items, the complexity of the items, and the risk associated with the items.

  3. Order the Items: After prioritizing, the items are ordered in the product backlog. The items with the highest value are placed at the top of the backlog so that they can be developed first. The items with lower value are placed lower in the backlog.

  4. Review and Update: The product backlog is not a static document. It should be regularly reviewed and updated. As new items come up, they should be added to the backlog. As items are completed, they should be removed from the backlog. And as the value of items changes, the order of the backlog should be updated.

So, while complexity, team choice, and risk are factors that can influence the order of the product backlog, the primary factor should be the value of the items being delivered.

This problem has been solved

Similar Questions

Who is responsible for prioritizing the product backlog?I.Product OwnerII.Scrum Team III.StakeholderIV.Scrum Master

Question 12Select the correct statement regarding product backlog.1 pointThe product backlog is ordered by importance or business value.Putting items in the icebox creates clutter in the product backlog.The stories at the bottom of the backlog are the most detailed.Epic stories are automatically put first in the product backlog.

Question 7Select the correct statement regarding product backlog. 1 pointThe product backlog is ordered by importance. The stories at the bottom of the backlog are the most detailed. The product backlog is ordered by which stories follow the template. Epic stories are automatically put first in the product backlog.

When building a Product Backlog, you compare the importance of each Backlog item to the other Backlog items. This helps you rank and organize the Backlog items from highest to lowest priority. You should capture this information in which Backlog item attribute? 1 pointItem effort estimateItem valueItem orderItem description

The product backlog consists of stories _____.1 pointin which stories are refined to be clearer and more directin which epic stories are put first, then in descending order by sizein the order in which they entered the backlog in order of importance and/or business value

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.