Select the correct answerP can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. Then Q alone can do it in?Options25 days30 days20 days15 days
Question
Select the correct answerP can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. Then Q alone can do it in?Options25 days30 days20 days15 days
Solution
To solve this problem, we need to understand the concept of work and time, and how they relate to each other in this context.
Step 1: Understand the problem The problem states that P can do a work in the same time in which Q and R together can do it. This means that the work rate of P is equal to the combined work rate of Q and R.
Step 2: Translate the problem into equations We know that work rate is work/time. So, we can write the first condition as: P = Q + R
The problem also states that P and Q together can complete the work in 10 days. This means that the combined work rate of P and Q is 1/10 work/day. We can write this as: P + Q = 1/10
Finally, the problem states that R alone needs 50 days to complete the same work. This means that the work rate of R is 1/50 work/day. We can write this as: R = 1/50
Step 3: Solve the equations We can substitute the value of R from the third equation into the first equation to get: P = Q + 1/50
Then, we can substitute the value of P from this equation into the second equation to get: Q + 1/50 + Q = 1/10 2Q + 1/50 = 1/10 2Q = 1/10 - 1/50 2Q = 4/50 Q = 4/50 / 2 Q = 2/50 Q = 1/25
So, Q alone can do the work in 25 days. Therefore, the correct answer is "25 days".
Similar Questions
Select the correct answerA work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days alone P can finish the work?Options10 days30 days60 days20 days
Select the correct answerP and Q together can do a job in 6 days. Q and R can finish the same job in 60/7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is?Options1581210
Select the correct answerP takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 Day’s if work together. How much time will Q take to do the work alone?Options5467
Select the correct answerP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?Options5 6/115 5/116 5/116 6/11
Select the correct answerA, B and C can do a work separately in 24, 36 and 48 days respectively. B leaves 7 days before completion and A left 3 days before completion. work will finish in how many days?Options11 5/1312 7/1314 8/1313 9/13
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.