Select the correct answerP and Q together can do a job in 6 days. Q and R can finish the same job in 60/7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is?Options1581210
Question
Select the correct answerP and Q together can do a job in 6 days. Q and R can finish the same job in 60/7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is?Options1581210
Solution
To solve this problem, we need to first find out the work done by P, Q, and R in one day.
-
P and Q together can do a job in 6 days. So, their combined work rate is 1/6 of the job per day.
-
Q and R together can do the same job in 60/7 days. So, their combined work rate is 7/60 of the job per day.
-
P started the work and worked for 3 days. So, P alone did 3*(1/6) = 1/2 of the job.
-
Q and R continued for 6 days. So, they together did 6*(7/60) = 7/10 of the job.
-
The total work done by P, Q, and R is 1/2 + 7/10 = 12/10 = 1.2 of the job. Since the total work cannot be more than 1, there must be an overlap in the work done by P and (Q, R). This overlap is the work done by Q, which is 1.2 - 1 = 0.2 of the job.
-
Since Q's work rate when working with P is (1/6) and when working with R is (7/60), we can set up the equation (1/6)x + (7/60)(6-x) = 0.2 to solve for x, which is the number of days Q worked with P. Solving this equation gives x = 2 days.
-
Therefore, Q worked with R for 6 - 2 = 4 days. Since Q and R together can do the job in 60/7 days, R alone can do the job in (60/7) / (1 - 1/6) = 10 days.
-
P alone can do the job in 6 / (1 - 1/10) = 15 days.
-
The difference in days in which R and P can complete the job is 15 - 10 = 5 days.
So, the correct answer is not in the options given. The difference should be 5 days.
Similar Questions
Select the correct answerP can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. Then Q alone can do it in?Options25 days30 days20 days15 days
Select the correct answerA work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days alone P can finish the work?Options10 days30 days60 days20 days
Select the correct answerP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?Options5 6/115 5/116 5/116 6/11
Select the correct answerA, B and C can do a work separately in 24, 36 and 48 days respectively. B leaves 7 days before completion and A left 3 days before completion. work will finish in how many days?Options11 5/1312 7/1314 8/1313 9/13
Select the correct answerA can finish one-third of a work in 5 days, B can finish 2/5th of the same work in 10 days and C can finish 75% of the same work in 15 days. They work together for 6 days; The remaining work will be finished by B alone in?Options3 days5 days2.5 days1.5 days
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.