Knowee
Questions
Features
Study Tools

Select the correct answerP and Q together can do a job in 6 days. Q and R can finish the same job in 60/7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is?Options1581210

Question

Select the correct answerP and Q together can do a job in 6 days. Q and R can finish the same job in 60/7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is?Options1581210

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we need to first find out the work done by P, Q, and R in one day.

  1. P and Q together can do a job in 6 days. So, their combined work rate is 1/6 of the job per day.

  2. Q and R together can do the same job in 60/7 days. So, their combined work rate is 7/60 of the job per day.

  3. P started the work and worked for 3 days. So, P alone did 3*(1/6) = 1/2 of the job.

  4. Q and R continued for 6 days. So, they together did 6*(7/60) = 7/10 of the job.

  5. The total work done by P, Q, and R is 1/2 + 7/10 = 12/10 = 1.2 of the job. Since the total work cannot be more than 1, there must be an overlap in the work done by P and (Q, R). This overlap is the work done by Q, which is 1.2 - 1 = 0.2 of the job.

  6. Since Q's work rate when working with P is (1/6) and when working with R is (7/60), we can set up the equation (1/6)x + (7/60)(6-x) = 0.2 to solve for x, which is the number of days Q worked with P. Solving this equation gives x = 2 days.

  7. Therefore, Q worked with R for 6 - 2 = 4 days. Since Q and R together can do the job in 60/7 days, R alone can do the job in (60/7) / (1 - 1/6) = 10 days.

  8. P alone can do the job in 6 / (1 - 1/10) = 15 days.

  9. The difference in days in which R and P can complete the job is 15 - 10 = 5 days.

So, the correct answer is not in the options given. The difference should be 5 days.

This problem has been solved

Similar Questions

Select the correct answerP can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. Then Q alone can do it in?Options25 days30 days20 days15 days

Select the correct answerA work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days alone P can finish the work?Options10 days30 days60 days20 days

Select the correct answerP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?Options5 6/115 5/116 5/116 6/11

Select the correct answerA, B and C can do a work separately in 24, 36 and 48 days respectively. B leaves 7 days before completion and A left 3 days before completion. work will finish in how many days?Options11 5/1312 7/1314 8/1313 9/13

Select the correct answerA can finish one-third of a work in 5 days, B can finish 2/5th of the same work in 10 days and C can finish 75% of the same work in 15 days. They work together for 6 days; The remaining work will be finished by B alone in?Options3 days5 days2.5 days1.5 days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.