Knowee
Questions
Features
Study Tools

Select the correct answerA work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days alone P can finish the work?Options10 days30 days60 days20 days

Question

Select the correct answerA work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days alone P can finish the work?Options10 days30 days60 days20 days

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we need to find the rates at which P, Q, and R work.

  1. P and Q can complete the work in 12 days, so their combined rate is 1/12 of the work per day.
  2. Q and R can complete the work in 15 days, so their combined rate is 1/15 of the work per day.
  3. R and P can complete the work in 20 days, so their combined rate is 1/20 of the work per day.

If we add these three rates together, we get (1/12 + 1/15 + 1/20) = 1/4 of the work per day. But this is twice the sum of the rates of P, Q, and R (because each is counted twice in the sum), so the sum of the rates of P, Q, and R is (1/4)/2 = 1/8 of the work per day.

If we subtract the rates of Q and R from this, we can find the rate of P:

The rate of Q and R is 1/15 of the work per day, so the rate of P is (1/8 - 1/15) = 7/120 of the work per day.

Therefore, P can complete the work alone in 120/7 days, which is approximately 17.14 days.

However, this is not one of the options given. It seems there may be a mistake in the problem or the options provided.

This problem has been solved

Similar Questions

Select the correct answerP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?Options5 6/115 5/116 5/116 6/11

Select the correct answerP can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. Then Q alone can do it in?Options25 days30 days20 days15 days

Select the correct answerA, B and C can do a work in 20 days, 24 days and 30 days respectively. A and B left the work 4 days before completion of the work, then whole work will finish in how many days?Options10 14/1511 8/159 2/312 7/15

Select the correct answerA can complete a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?Options7 days8 days8.5 days7.5 days

Select the correct answerA can finish one-third of a work in 5 days, B can finish 2/5th of the same work in 10 days and C can finish 75% of the same work in 15 days. They work together for 6 days; The remaining work will be finished by B alone in?Options3 days5 days2.5 days1.5 days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.