Select the correct answerA can complete a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?Options7 days8 days8.5 days7.5 days
Question
Select the correct answerA can complete a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?Options7 days8 days8.5 days7.5 days
Solution
Sure, let's solve this step by step:
-
First, we need to find out how much work A and B can do in a day. If A can complete the work in 15 days, then A can do 1/15 of the work in a day. Similarly, if B can complete the work in 10 days, then B can do 1/10 of the work in a day.
-
Next, we need to find out how much work B has already done. If B worked for 5 days, and B can do 1/10 of the work in a day, then B has done 5 * (1/10) = 1/2 of the work.
-
Now, we need to find out how much work is left. If B has done 1/2 of the work, then there is 1 - 1/2 = 1/2 of the work left.
-
Finally, we need to find out how long it will take A to finish the remaining work. If A can do 1/15 of the work in a day, then it will take A 1/2 / (1/15) = 7.5 days to finish the remaining work.
So, the correct answer is 7.5 days.
Similar Questions
Select the correct answerA can finish one-third of a work in 5 days, B can finish 2/5th of the same work in 10 days and C can finish 75% of the same work in 15 days. They work together for 6 days; The remaining work will be finished by B alone in?Options3 days5 days2.5 days1.5 days
Select the correct answerA and B together can finish a work in 6.75 days. A alone can finish the same work in 9 days. In how many days will B alone finish the work?Options27 days18 days35 days36 days
Select the correct answerA, B, C can do a work in 5 days, 10 days and 15 days respectively. They started together to do the work but after 2 days A and B left. C did the remaining work in how many days?Options3 days4 days3 1/2days2 days
A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone finish the whole work?Options2.5 days, 7.5 days5 days, 15 daysNone of these5 days, 8.5 days
Select the correct answerA work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days alone P can finish the work?Options10 days30 days60 days20 days