Knowee
Questions
Features
Study Tools

Select the correct answerA, B and C can do a work separately in 24, 36 and 48 days respectively. B leaves 7 days before completion and A left 3 days before completion. work will finish in how many days?Options11 5/1312 7/1314 8/1313 9/13

Question

Select the correct answerA, B and C can do a work separately in 24, 36 and 48 days respectively. B leaves 7 days before completion and A left 3 days before completion. work will finish in how many days?Options11 5/1312 7/1314 8/1313 9/13

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we first need to find the rate at which A, B, and C work.

  1. A's work rate is 1/24 of the work per day (since A can complete the work in 24 days).
  2. B's work rate is 1/36 of the work per day (since B can complete the work in 36 days).
  3. C's work rate is 1/48 of the work per day (since C can complete the work in 48 days).

Next, we need to find out how much work is done by A, B, and C until B and A leave.

  1. B leaves 7 days before completion, so B works for the entire time minus 7 days.
  2. A leaves 3 days before completion, so A works for the entire time minus 3 days.
  3. C works for the entire time.

Let's denote the total time needed to complete the work as T.

So, the total work done (which is 1, since it's the whole work) can be expressed as:

(1/24)(T-3) + (1/36)(T-7) + (1/48)*T = 1

To solve this equation for T, we first need to find a common denominator for the fractions, which is 288.

So, the equation becomes:

12*(T-3) + 8*(T-7) + 6*T = 288

Solving this equation gives:

12T - 36 + 8T - 56 + 6T = 288 26T - 92 = 288 26T = 380 T = 380 / 26 T = 14 12/26 = 14 8/13

So, the work will be finished in 14 8/13 days.

Therefore, the correct answer is 14 8/13.

This problem has been solved

Similar Questions

Select the correct answerA, B and C can do a work in 20 days, 24 days and 30 days respectively. A and B left the work 4 days before completion of the work, then whole work will finish in how many days?Options10 14/1511 8/159 2/312 7/15

A can finish a work in 24 days, B in 9 days and C in 12 days. B & C start the work but are forced to leave after 3 days. The remaining work done by A in:

Select the correct answerA and B together can finish a work in 6.75 days. A alone can finish the same work in 9 days. In how many days will B alone finish the work?Options27 days18 days35 days36 days

Select the correct answerA, B and C can do a piece of work in 30 days, 45 days and 90 days, respectively. A starts the work and he is assisted by B and C together on every third day. In how many days will the work be completed?Options24233022

Select the correct answerA can do 7/8 of work in 28 days, B can do 5/6 of the same work in 20 days. The number of days they will take to complete if they do it together is?Options15 7/3 days14 5/7 days13 5/7 days17 3/5 days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.