Based on this figure,what would you do in project scheduling? TIME PARKINSON'S LAW EFFORT O I avoid assigning tough(short)durations to activities OI avoid assigning generous(long)durations to activities ○I avoid assigning realistic duration to activities O I will assign generous buffer to the critical path activities
Question
Based on this figure,what would you do in project scheduling? TIME PARKINSON'S LAW EFFORT O I avoid assigning tough(short)durations to activities OI avoid assigning generous(long)durations to activities ○I avoid assigning realistic duration to activities O I will assign generous buffer to the critical path activities
Solution
Based on the figure, the best approach to project scheduling would be to avoid assigning generous (long) durations to activities. This is because of Parkinson's Law, which states that "work expands so as to fill the time available for its completion". If you assign a long duration to an activity, there's a high chance that the team will use up all that time, even if the task could have been completed sooner. Therefore, it's more efficient to assign realistic durations to activities.
However, it's also important not to assign overly short durations, as this could lead to stress and rushed work.
Lastly, while it's not always necessary to assign a generous buffer to critical path activities, it can be a good idea to allow some extra time for these tasks, as any delay could impact the entire project.
So, in summary:
- Avoid assigning generous (long) durations to activities.
- Avoid assigning overly short durations to activities.
- Assign realistic durations to activities.
- Consider assigning a generous buffer to critical path activities.
Similar Questions
Based on this figure,what would you do in project scheduling? TIME PARKINSON'S LAW EFFORT O I avoid assigning tough(short)durations to activities OI avoid assigning generous(long)durations to activities ○I avoid assigning realistic duration to activities O I will assign generous buffer to the critical path activities
Mention the inputs, tools and techniques, and outputs of two of the following processes in project schedule management:Sequence activitiesDevelop scheduleEstimate activity duration
The activity that distributes estimated effort across the planned project duration by allocating the effort to specific software developing tasks is ____________ .Option 1None of the mentionedOption 2Project schedulingOption 3Detailed scheduleOption 4Macroscopic schedule
Which of the following is the longest string of dependent project activities required to complete a project in the shortest amount of time? Effort estimateProject scheduleResource estimateCritical path
Since all activities along the critical chain have inherent uncertainty that is difficult to predict, project duration is uncertain. Therefore, this type of buffer is added to the expected project duration.Multiple choice question.Project bufferBurst buffersResource buffersFeeder buffersMerge buffers
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.