Mention the inputs, tools and techniques, and outputs of two of the following processes in project schedule management:Sequence activitiesDevelop scheduleEstimate activity duration
Question
Mention the inputs, tools and techniques, and outputs of two of the following processes in project schedule management:Sequence activitiesDevelop scheduleEstimate activity duration
Solution
Sure, let's discuss two of the processes in project schedule management: Sequence Activities and Develop Schedule.
-
Sequence Activities:
- Inputs: The inputs for this process include the project management plan, project documents like the activity list, activity attributes, milestone list, project scope statement, enterprise environmental factors, and organizational process assets.
- Tools and Techniques: The tools and techniques used in this process are precedence diagramming method (PDM), dependency determination and integration, leads and lags, and project management information system (PMIS).
- Outputs: The outputs of this process are project schedule network diagrams, project documents updates including activity list, activity attributes, and milestone list.
-
Develop Schedule:
- Inputs: The inputs for this process include the project management plan, project documents like the activity list, activity attributes, project schedule network diagrams, assumption log, basis of estimates, project team assignments, resource calendars, risk register, and agreements. Other inputs include enterprise environmental factors and organizational process assets.
- Tools and Techniques: The tools and techniques used in this process are schedule network analysis, critical path method, critical chain method, resource optimization, data analysis, leads and lags, schedule compression, project management information system (PMIS), agile release planning.
- Outputs: The outputs of this process are the schedule baseline, project schedule, schedule data, project calendars, project management plan updates, project documents updates including assumption log, basis of estimates, and risk register.
Similar Questions
Which process in project schedule management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?Group of answer choicesestimating activity durationssequencing activitiesdefining activitiesdeveloping the schedule
After working with key stakeholders to define activities and calculate their resources, what is the next process in project schedule management?Group of answer choicesdetermine their dependenciesdevelop the schedule.estimate the duration of activitiescontrol the schedule.
In project schedule management, the main goal of which process is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work?Group of answer choicesestimating activity durationsestimating activity resourcesdefining activitiescontrolling the schedule
Which of the following provides a sequenced plan that estimates the time required to complete project activities and tasks?Project planProject scheduleCommunication planResource plan
In project schedule management, the process of _____ involves deciding how many people, equipment, and materials a project team should use to perform project activities.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.