Which of the following is the longest string of dependent project activities required to complete a project in the shortest amount of time? Effort estimateProject scheduleResource estimateCritical path

Question

Which of the following is the longest string of dependent project activities required to complete a project in the shortest amount of time? Effort estimateProject scheduleResource estimateCritical path

🧐 Not the exact question you are looking for?Go ask a question

Solution

The longest string of dependent project activities required to complete a project in the shortest amount of time is the Critical path.

Similar Questions

Which of the following provides a sequenced plan that estimates the time required to complete project activities and tasks?Project planProject scheduleCommunication planResource plan

Which path duration is considered as the project completion timea.Shortest pathb.Longest Pathc.Most likely pathd.None of the given options

The activity that distributes estimated effort across the planned project duration by allocating the effort to specific software developing tasks is ____________ .Option 1None of the mentionedOption 2Project schedulingOption 3Detailed scheduleOption 4Macroscopic schedule

Which of the following is the total time it takes to complete a project from start to finish?1 pointDurationMilestoneIssueTask

Which of the following does NOT affect a time estimate?Effort estimatesSchedule dependenciesCommunication requirementsEquipment availability