Which of the following is the longest string of dependent project activities required to complete a project in the shortest amount of time? Effort estimateProject scheduleResource estimateCritical path
Question
Which of the following is the longest string of dependent project activities required to complete a project in the shortest amount of time? Effort estimateProject scheduleResource estimateCritical path
Solution
The longest string of dependent project activities required to complete a project in the shortest amount of time is the Critical path.
Similar Questions
Which of the following provides a sequenced plan that estimates the time required to complete project activities and tasks?Project planProject scheduleCommunication planResource plan
Which path duration is considered as the project completion timea.Shortest pathb.Longest Pathc.Most likely pathd.None of the given options
The activity that distributes estimated effort across the planned project duration by allocating the effort to specific software developing tasks is ____________ .Option 1None of the mentionedOption 2Project schedulingOption 3Detailed scheduleOption 4Macroscopic schedule
Which of the following is the total time it takes to complete a project from start to finish?1 pointDurationMilestoneIssueTask
Which of the following does NOT affect a time estimate?Effort estimatesSchedule dependenciesCommunication requirementsEquipment availability
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.