n a network flow diagram, two jobs (i,j) and (i,k) of ‘9’and ‘6’ days duration leaves the node ‘i’ then which ofthe following will be Late start time for ‘i’, if it is provided that both (i,j) and (i,k) finish late on 12th and 8th dayrespectively?Select correct option:6th day2nd day3rd day1st day

Question

n a network flow diagram, two jobs (i,j) and (i,k) of ‘9’and ‘6’ days duration leaves the node ‘i’ then which ofthe following will be Late start time for ‘i’, if it is provided that both (i,j) and (i,k) finish late on 12th and 8th dayrespectively?Select correct option:6th day2nd day3rd day1st day

🧐 Not the exact question you are looking for?Go ask a question

Solution

In a network flow diagram, the Late Start time for a particular task is calculated by subtracting the task's duration from its Late Finish time.

Here, we have two tasks (i,j) and (i,k) with durations of 9 and 6 days respectively. They finish late on the 12th and 8th day respectively.

For task (i,j): Late Finish time = 12th day Duration = 9 days So, Late Start time for (i,j) = Late Finish - Duration = 12 - 9 = 3rd day

For task (i,k): Late Finish time = 8th day Duration = 6 days So, Late Start time for (i,k) = Late Finish - Duration = 8 - 6 = 2nd day

However, in a network flow diagram, the Late Start time for a node is determined by the latest start time among all tasks leaving that node.

So, the Late Start time for node 'i' will be the later of the two calculated Late Start times, which is the 3rd day.

Therefore, the correct option is 3rd day.

This problem has been solved

Similar Questions

If both jobs ‘a(l,n)’ and ‘b(m,n)’ of ‘7’ and ‘8’ days durationsrespectively, start earlier simultaneously on 4th day, then ‘n’ can start earlieron -----------day. 8th 11th 15t

In a development project, if an activity (i,j) of six days duration, starts late on 3rd day then which of thefollowing will be its latest finish time?Select correct option:9th day2nd day3rd day18th day

The following table shows jobs to be processed at a machine. Determine the processing sequence that will minimize total number of late jobs.   Job Processing Time (days) Due Date (days)   A 3   4    B 2   5    C 5 10   D 2 11   E 4 13   F 9 201. Job is the first job that is late in the given sequence.2. Job has the largest processing time out of these 5 jobs.3. Optimal sequence is with on

Select the correct answerP and Q together can do a job in 6 days. Q and R can finish the same job in 60/7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is?Options1581210

Select the correct answerA, B and C can do a work separately in 24, 36 and 48 days respectively. B leaves 7 days before completion and A left 3 days before completion. work will finish in how many days?Options11 5/1312 7/1314 8/1313 9/13

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.