Knowee
Questions
Features
Study Tools

A and B working together, can do a piece of work in 4 1/2hours. B and C working together can do it in 3 hours. C and A working together can do it in 2 1/4hours. All of them begin the work at the same time. Find how much time they will take to finish the piece of work?Options3 hours2·5 hours3·25 hours2 hours

Question

A and B working together, can do a piece of work in 4 1/2hours. B and C working together can do it in 3 hours. C and A working together can do it in 2 1/4hours. All of them begin the work at the same time. Find how much time they will take to finish the piece of work?Options3 hours2·5 hours3·25 hours2 hours

🧐 Not the exact question you are looking for?Go ask a question

Solution 1

To solve this problem, we need to find the rates at which A, B, and C work.

  1. A and B together can complete the work in 4.5 hours. So, their combined rate is 1/4.5 = 0.2222 work/hour.
  2. B and C together can complete the work in 3 hours. So, their combined rate is 1/3 = 0.3333 work/hour.
  3. C and A together can complete the work in 2.25 hours. So, their combined rate is 1/2.25 = 0.4444 work/hour.

Now, if we add up the rates of A and B, B and C, and C and A, we get twice the total rate of A, B, and C. So, the total rate of A, B, and C is (0.2222 + 0.3333 + 0.4444) / 2 = 0.5 work/hour.

Therefore, all of them working together can complete the work in 1/0.5 = 2 hours. So, the correct answer is 2 hours.

This problem has been solved

Solution 2

To solve this problem, we need to find the rates at which A, B, and C work.

  1. A and B together can complete the work in 4.5 hours. So, their combined rate is 1/4.5 = 0.2222 work/hour.
  2. B and C together can complete the work in 3 hours. So, their combined rate is 1/3 = 0.3333 work/hour.
  3. C and A together can complete the work in 2.25 hours. So, their combined rate is 1/2.25 = 0.4444 work/hour.

Now, if we add up the rates of A and B, B and C, and C and A, we get twice the total rate of A, B, and C. So, the total rate of A, B, and C is (0.2222 + 0.3333 + 0.4444) / 2 = 0.5 work/hour.

Therefore, A, B, and C together can complete the work in 1/0.5 = 2 hours. So, the correct answer is 2 hours.

This problem has been solved

Similar Questions

A can do as much work as B and C together can do. A and B can together do a piece of work in 9 hours 36 minutes and C can do it in 48 hours. The time (in hours) that B needs to do the work alone, is?Options18 hrs24 hrs30 hrs12 hrs

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:4 days6 days8 days12 days

A, B and C can do a piece of work in 20, 30 and 40 days, respectively. A and C started the work and B joined 4 days later. A left 8 days before the completion of work and C was also absent for 5 days in between. How many days will it take for the work to be completed?

A and B can do a piece of work in 3 days, B and C in 4 days, C and A in 6 days. How long will C take to do it?a.24 daysb.20 daysc.18 daysd.30 days

A, B and C can do a work in 5 days, 10 days and 15 days respectively. They started together to do the work but after 2 days A and B left. C did the remaining work (in days)

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.