Knowee
Questions
Features
Study Tools

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:4 days6 days8 days12 days

Question

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:4 days6 days8 days12 days

🧐 Not the exact question you are looking for?Go ask a question

Solution

Let's denote the amount of work as W.

  1. According to the problem, A takes twice as much time as B to finish the work, so we can say that the work rate of A is 1/2 of B. We denote this as A = 1/2B.

  2. Similarly, A takes thrice as much time as C to finish the work, so the work rate of A is 1/3 of C. We denote this as A = 1/3C.

  3. Working together, A, B, and C can finish the work in 2 days. This means that 2(A + B + C) = W.

  4. We can substitute A from the first and second equations into the third equation to get: 2((1/2B + B + 1/3C) = W. Simplifying this gives us B + C = W/2.

  5. From the problem, we know that B can do the work alone in x days. This means that B = W/x.

  6. Substituting B = W/x into the equation B + C = W/2 gives us W/x + C = W/2. Solving for C gives us C = W/2 - W/x.

  7. Substituting C = W/2 - W/x into the equation A = 1/3C gives us A = 1/3(W/2 - W/x). Simplifying this gives us A = W/6 - W/3x.

  8. Substituting A = W/6 - W/3x and B = W/x into the equation 2(A + B + C) = W gives us 2((W/6 - W/3x) + W/x + (W/2 - W/x)) = W. Simplifying this gives us W/3 + W/2 = W.

  9. Solving for x gives us x = 6.

Therefore, B can do the work alone in 6 days.

This problem has been solved

Similar Questions

A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days. A alone will take to finish the job is

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :8 days10 days12 days15 days

A can do a piece of work in 4 hours. B and C can do the same piece of work together in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?Marks : 1Negative Marks : 0Answer here12638

A and B can do a work in 30 days. If A worked twice as fast and B worked one-fourth as efficiently as he usually does, the work would still be completed in 30 days. Find the time taken (in days) by A alone to do the work.

A and B can do a piece of work in 6 2/3 days and 5 days respectively. They work together for 2 days and then A leaves. In how many days after that B will complete the work alone.a.3 ½ daysb.2 daysc.1 ½ daysd.3 days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.