A can do a piece of work in 4 hours. B and C can do the same piece of work together in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?Marks : 1Negative Marks : 0Answer here12638

Question

A can do a piece of work in 4 hours. B and C can do the same piece of work together in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?Marks : 1Negative Marks : 0Answer here12638

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we need to find the rates at which A, B, and C work.

  1. A can do the work in 4 hours, so A's rate of work is 1/4 of the work per hour.
  2. B and C together can do the work in 3 hours, so their combined rate is 1/3 of the work per hour.
  3. A and C together can do the work in 2 hours, so their combined rate is 1/2 of the work per hour.

We can set up the following equation to find B's rate of work:

(A's rate) + (B's rate) = (A and C's rate) + (B and C's rate)

Substituting the known rates, we get:

1/4 + B's rate = 1/2 + 1/3

Solving for B's rate, we find that B's rate is 1/12 of the work per hour.

Therefore, B alone will take 12 hours to do the work.

This problem has been solved

Similar Questions

A and B working together, can do a piece of work in 4 1/2hours. B and C working together can do it in 3 hours. C and A working together can do it in 2 1/4hours. All of them begin the work at the same time. Find how much time they will take to finish the piece of work?

A can do as much work as B and C together can do. A and B can together do a piece of work in 9 hours 36 minutes and C can do it in 48 hours. The time (in hours) that B needs to do the work alone, is?Options18 hrs24 hrs30 hrs12 hrs

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:4 days6 days8 days12 days

Select the correct answerA takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is?Options961009590

A can do a piece of work in 4 days. B can do it in 5 days. With the assistance of C they completed the work in 2 days. Find in how many days can C alone do it?a.4 daysb.5 daysc.20 daysd.10 days

1/3