Knowee
Questions
Features
Study Tools

A, B and C can do a piece of work in 20, 30 and 40 days, respectively. A and C started the work and B joined 4 days later. A left 8 days before the completion of work and C was also absent for 5 days in between. How many days will it take for the work to be completed?

Question

A, B and C can do a piece of work in 20, 30 and 40 days, respectively. A and C started the work and B joined 4 days later. A left 8 days before the completion of work and C was also absent for 5 days in between. How many days will it take for the work to be completed?

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we first need to find out the work done by A, B, and C in one day.

  1. A's one day work = 1/20
  2. B's one day work = 1/30
  3. C's one day work = 1/40

Next, we need to calculate the total work done by A and C before B joined them. They worked together for 4 days, so:

Work done by A and C in 4 days = 4 * (1/20 + 1/40) = 4 * (3/60) = 4/20 = 1/5 of the total work.

Now, let's calculate the remaining work: 1 - 1/5 = 4/5.

Let's assume that the remaining work is completed in 'x' days.

In these 'x' days, A worked for (x - 8) days (since A left 8 days before the completion), B worked for x days, and C worked for (x - 5) days (since C was absent for 5 days).

So, the equation for the remaining work is:

(x - 8)/20 + x/30 + (x - 5)/40 = 4/5

To solve this equation, we first make the denominators the same, which is 120 in this case. The equation becomes:

6*(x - 8) + 4x + 3(x - 5) = 96

Solving this equation gives us x = 15.

So, the total time taken to complete the work is 4 (initial days when A and C worked) + 15 = 19 days.

This problem has been solved

Similar Questions

A, B and C can do a work in 20 days, 24 days and 30 days respectively. A and B left the work 4 days before completion of the work, then whole work will finish in how many days?Options10 14/1512 7/1511 8/159 2/3

A can do a piece of work in 5 days and B in 20 days. They work together for 2 days and then both leave the work. Then C alone can finish the remaining work in 6 days. In how many days will C finish the full work?

A and B can separately do a work in 40 days & 30 days . They worked together for 10 days after which B was replaced by C . If the work was finished in next 40/3 days, the number of days in which C alone could do the work?

A can do a piece of work in 8 days and B can do the same work in 10 days. They started the work together but after 3 days, A left . In how many days B can complete the remaining work?4 days7 days7.5 days3. 25 days

A, B and C can do a piece of work in 30 days, 45 days and 90 days, respectively. A starts the work and he is assisted by B and C together on every third day. In how many days will the work be completed?Options23302224

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.