PERT is use full when we have following time duration except:a.Optimistic timeb.Pessimistic timec.Most likely timed.Certain Duration
Question
PERT is use full when we have following time duration except:a.Optimistic timeb.Pessimistic timec.Most likely timed.Certain Duration
Solution
The PERT (Program Evaluation and Review Technique) is a statistical tool used in project management, which is designed to analyze and represent the tasks involved in completing a given project. It incorporates uncertainty by making it possible to schedule a project while not knowing precisely the details and durations of all the activities.
The time estimates in PERT include:
a. Optimistic time: the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected.
b. Pessimistic time: the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).
c. Most likely time: the best estimate of the time required to accomplish a task, assuming everything proceeds as normal.
The option that PERT does not use is:
d. Certain Duration: PERT is designed to handle uncertainty in activity completion times. Therefore, it does not use a certain duration as it assumes there is always some degree of uncertainty in how long each task will take.
Similar Questions
PERT is a three time estimate and gives more weightage toQuestion 3Answera.Optimistic timeb.Most likely timec.Pessimistic timed.Expected time
Time used in PERT for drawing the Network diagram is a.Optimistic timeb.Pessimistic timec.Most likely timed.Expected Time
hile solving a network flow problem by PERT, which of the followingtype of time will be used to measure the length of Critical Path? Pessimistic Expected Most Likely Optimistic
A CPM/PERT project network with probabilistic activity times includes an activity with a most likely time of 18 days, an optimistic time of 5 days, and a pessimistic time of 23 days. The mean time for this activity is (round to the nearest whole number)
A PERT/CPM activity has an optimistic time estimate of 5 days, a most likely time estimate of 10 days, and a pessimistic time estimate of 24 days. What is the expected time (in days) of this activity?Round answer to two decimal places.hint: formula is available in lecture notes