Time used in PERT for drawing the Network diagram is a.Optimistic timeb.Pessimistic timec.Most likely timed.Expected Time

Question

Time used in PERT for drawing the Network diagram is a.Optimistic timeb.Pessimistic timec.Most likely timed.Expected Time

🧐 Not the exact question you are looking for?Go ask a question

Solution

The time used in PERT (Program Evaluation Review Technique) for drawing the Network diagram is the Expected Time.

Here's why:

a. Optimistic time: This is the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected.

b. Pessimistic time: This is the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).

c. Most likely time: This is the best estimate of the time required to accomplish a task, assuming everything proceeds as normal.

d. Expected Time: This is the best estimate of the time required to accomplish a task, taking into account the risk or uncertainty in the time estimation. It is calculated as (Optimistic time + 4*Most likely time + Pessimistic time) / 6.

This problem has been solved

Similar Questions

hile solving a network flow problem by PERT, which of the followingtype of time will be used to measure the length of Critical Path? Pessimistic Expected Most Likely Optimistic

PERT is a three time estimate and gives more weightage toQuestion 3Answera.Optimistic timeb.Most likely timec.Pessimistic timed.Expected time

A CPM/PERT project network with probabilistic activity times includes an activity with a most likely time of 18 days, an optimistic time of 5 days, and a pessimistic time of 23 days. The mean time for this activity is  (round to the nearest whole number)

PERT is use full when we have following time duration except:a.Optimistic timeb.Pessimistic timec.Most likely timed.Certain Duration

A PERT/CPM activity has an optimistic time estimate of 5 days, a most likely time estimate of 10 days, and a pessimistic time estimate of 24 days. What is the expected time (in days) of this activity?Round answer to two decimal places.hint: formula is available in lecture notes