A started a work and left working after 9 days now B finished the remaining work in 24 days. Had A left the work after working for 13 days then B would have finished the remaining work in next 18 days. Then find in how many days A and B together can complete the work?Options12 days15 days16 days18 days
Question
A started a work and left working after 9 days now B finished the remaining work in 24 days. Had A left the work after working for 13 days then B would have finished the remaining work in next 18 days. Then find in how many days A and B together can complete the work?Options12 days15 days16 days18 days
Solution
To solve this problem, we need to first understand the concept of work and time. The amount of work done by a person is inversely proportional to the time taken.
Step 1: Let's assume the total work to be done is 1 unit.
Step 2: From the problem, we know that A works for 9 days and B finishes the remaining work in 24 days. This means that the work done by A in 1 day + the work done by B in 1 day = 1/33 (since 9 days of A + 24 days of B = 33 days to complete 1 unit of work).
Step 3: Similarly, if A works for 13 days and B finishes the remaining work in 18 days, the work done by A in 1 day + the work done by B in 1 day = 1/31 (since 13 days of A + 18 days of B = 31 days to complete 1 unit of work).
Step 4: Now, we have two equations and two unknowns (the work done by A in 1 day and the work done by B in 1 day). We can solve these equations simultaneously to find the values.
Step 5: Subtracting the second equation from the first, we get the work done by A in 1 day = 1/33 - 1/31 = 2/ (33*31).
Step 6: Substituting this value in the first equation, we get the work done by B in 1 day = 1/33 - 2/(3331) = 1/(3331).
Step 7: Now, if A and B work together, the work done in 1 day = work done by A in 1 day + work done by B in 1 day = 2/(3331) + 1/(3331) = 3/(33*31).
Step 8: Therefore, the total time taken by A and B to complete the work together = 1 / (work done in 1 day) = 33*31/3 = 341 days.
However, this is not one of the options given. There might be a mistake in the problem or the options provided.
Similar Questions
A and B together can finish a work in 6.75 days. A alone can finish the same work in 9 days. In how many days will B alone finish the work?Options18 days27 days35 days36 days
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :8 days10 days12 days15 days
A can do a piece of work in 8 days and B can do the same work in 10 days. They started the work together but after 3 days, A left . In how many days B can complete the remaining work?4 days7 days7.5 days3. 25 days
A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone finish the whole work?Options2.5 days, 7.5 days5 days, 8.5 days5 days, 15 daysNone of these
A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave?Options7 5/9 days8 days9 days14 2/5 days
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.