A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave?Options7 5/9 days8 days9 days14 2/5 days

Question

A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave?Options7 5/9 days8 days9 days14 2/5 days

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we need to first understand the work rate of A and B.

  1. A can complete the work in 28 days, so A's work rate is 1/28 work/day.
  2. B can complete the work in 35 days, so B's work rate is 1/35 work/day.

When they work together, their combined work rate is 1/28 + 1/35 = 9/140 work/day.

Given that B alone completed the remaining work in 17 days, the amount of work done by B alone is 17 * (1/35) = 17/35 of the work.

Since the total work is 1, the work done by A and B together before A left is 1 - 17/35 = 18/35 of the work.

Let's denote the number of days A worked as x. So, the equation based on the work done by A and B together is:

x * (9/140) = 18/35

Solving this equation for x gives us:

x = (18/35) * (140/9) = 56/9 = 6 2/9 days.

So, A worked for approximately 6 2/9 days before leaving. However, this option is not available in the given options. There might be a mistake in the problem or the options.

This problem has been solved

Similar Questions

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :8 days10 days12 days15 days

A started a work and left working after 9 days now B finished the remaining work in 24 days. Had A left the work after working for 13 days then B would have finished the remaining work in next 18 days. Then find in how many days A and B together can complete the work?Options12 days16 days18 days15 days

A and B can do a piece of work in 45 and 40 days respectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after

A can finish a work in 24 days, B in 9 days and C in 12 days. B & C start the work but are forced to leave after 3 days. The remaining work done by A in:

A and B can do a piece of work in 6 2/3 days and 5 days respectively. They work together for 2 days and then A leaves. In how many days after that B will complete the work alone.a.3 ½ daysb.2 daysc.1 ½ daysd.3 days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.