A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone finish the whole work?Options2.5 days, 7.5 days5 days, 8.5 days5 days, 15 daysNone of these

Question

A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone finish the whole work?Options2.5 days, 7.5 days5 days, 8.5 days5 days, 15 daysNone of these

🧐 Not the exact question you are looking for?Go ask a question

Solution

This problem can be solved using the concept of work and efficiency in time and work problems.

Step 1: Let's denote the total work to be done as 1 unit.

Step 2: From the problem, we know that A works for 2 days and B finishes the remaining work in 9 days. This can be written as: 2A + 9B = 1 ---- (equation 1)

Step 3: The problem also states that if A had worked for 3 days, B would have finished the remaining work in 6 days. This can be written as: 3A + 6B = 1 ---- (equation 2)

Step 4: Now, we have two equations with two variables. We can solve these equations to find the values of A and B.

Subtract equation 2 from equation 1, we get: -1A + 3B = 0 => A = 3B ---- (equation 3)

Step 5: Substitute equation 3 in equation 1, we get: 2(3B) + 9B = 1 => 15B = 1 => B = 1/15

Step 6: Substitute B = 1/15 in equation 3, we get: A = 3(1/15) = 1/5

So, A can finish the work in 5 days and B can finish the work in 15 days. Therefore, the answer is 5 days, 15 days.

This problem has been solved

Similar Questions

A and B together can finish a work in 6.75 days. A alone can finish the same work in 9 days. In how many days will B alone finish the work?Options18 days27 days35 days36 days

Select the correct answerA and B together can finish a work in 5 days. If A works twice his efficiency they can finish the same work in 3 days. In how many days will A alone finish the work?Options5.4 days7.5 days6.6 days15 days

A can do a piece of work in 8 days and B can do the same work in 10 days. They started the work together but after 3 days, A left . In how many days B can complete the remaining work?4 days7 days7.5 days3. 25 days

A started a work and left working after 9 days now B finished the remaining work in 24 days. Had A left the work after working for 13 days then B would have finished the remaining work in next 18 days. Then find in how many days A and B together can complete the work?Options12 days15 days16 days18 days

A can finish one-third of a work in 5 days, B can finish 2/5th of the same work in 10 days and C can finish 75% of the same work in 15 days. They work together for 6 days; The remaining work will be finished by B alone in?Options5 days3 days2.5 days1.5 days