To crash a schedule, you should?a.Replace those workers that are not performing up to par with the busy.b.Increase work efforts on those tasks that are on the critical path.c.Increase the time allowed on those tasks that have float.d.Try to increase expenditures of time only those tasks that are behind schedule.

Question

To crash a schedule, you should?a.Replace those workers that are not performing up to par with the busy.b.Increase work efforts on those tasks that are on the critical path.c.Increase the time allowed on those tasks that have float.d.Try to increase expenditures of time only those tasks that are behind schedule.

🧐 Not the exact question you are looking for?Go ask a question

Solution

The best option to crash a schedule is b. Increase work efforts on those tasks that are on the critical path.

Here's why:

a. Replacing workers that are not performing up to par can be disruptive and may not necessarily speed up the project. It takes time for new workers to get up to speed.

b. The critical path is the sequence of tasks that must be completed on time for the project to finish on schedule. Any delay in these tasks will delay the project. Therefore, increasing work efforts on these tasks can help to crash the schedule.

c. Increasing the time allowed on tasks that have float will not help to crash the schedule. Float is the amount of time that you can delay a task without delaying the project. Therefore, these tasks are not on the critical path and increasing their time will not speed up the project.

d. Trying to increase expenditures of time only on tasks that are behind schedule may not be the most efficient way to crash the schedule. It's better to focus on the tasks on the critical path, whether they are behind schedule or not.

This problem has been solved

Similar Questions

Your project is 4 weeks behind schedule and you have been asked to crash the project in order to make up the lost time. The tasks listed in the table below are all on the critical path. Which of the tasks below would you crash?Tasks C & ETasks B & DTask A

Based on this figure,what would you do in project scheduling? TIME PARKINSON'S LAW EFFORT O I avoid assigning tough(short)durations to activities OI avoid assigning generous(long)durations to activities ○I avoid assigning realistic duration to activities O I will assign generous buffer to the critical path activities

What are some reasons project scheduling is not done well?

36. You are putting together the final schedule on your new project. The problem youare having is that you don’t have a consistent use of your resources. Some areworking 12 hours a day; some are working 4 hours a day; and some days theyaren’t scheduled to work at all. Which of the following below would fix the problem.a) Resource Levellingb) AON Analysisc) Fast Trackingd) Crashing7. You and a fellow Project Manager are having a discussion about his project. Hesays the Network diagram for it has two paths that have the maximum duration of32 units on the diagram. He says he doesn’t have a Critical Path because they areboth the same length, and you can only have one Critical Path. Which of thefollowing is a true statement?a) You can have more than one Critical Path, but they are the longest paths onthe project and more than on Critical Path will increase your project riskb) The Critical Path is the shortest path on the projectc) You can have more than one Critical Path, but they are the longest paths onthe project and more than on Critical Path will decrease your project riskd) You can have more than one Critical Path, but they are the shortest paths,not the longest

............... the most important task could be a solution to your time management, though it might be difficult to identify which one is the most necessary.PriorityIdentifyingPrioritizePrioritizing