4 men can repair a road in 7 hours. How many men are required to repair the road in 2 hours?
Question
4 men can repair a road in 7 hours. How many men are required to repair the road in 2 hours?
Solution
To solve this problem, we first need to understand the relationship between the number of men and the time it takes to repair the road.
Step 1: Find the work done by one man in one hour. Since 4 men can repair the road in 7 hours, one man would take 4 times as long to do the same job, so one man can repair the road in 4*7 = 28 hours.
Step 2: Find the amount of work one man can do in one hour. Since one man can complete the job in 28 hours, in one hour, he can complete 1/28 of the job.
Step 3: Find the number of men required to complete the job in 2 hours. If one man can do 1/28 of the job in one hour, in 2 hours, he can do 2/28 or 1/14 of the job. To complete the whole job in 2 hours, we would need 14 men (since 14*(1/14) = 1).
So, 14 men are required to repair the road in 2 hours.
Similar Questions
Ten men take 4 days to complete the task of tarring a road. How many days would8 men take?
The number of days needed in repairing a house varies inversely as the number of men working. It takes 15 days for 2 men to repair the house. How many men are needed to complete the job in 6 days?
A contractor agreed to construct a 12 km road in 180 days for which he employed 120 men. After 80 days construction of only 4 km road was completed. How many additional men should he employ to complete the work as per the agreement?
f 6 men can complete a work in 15 hours. Then how many hours it will take if 10 men working at the same speed complete the work?
Select the correct answer6 men finish one-forth work in 2 days. The number of additional men required for finishing the same work in 2 days is?Options18 men28 men14 men24 men