Knowee
Questions
Features
Study Tools

A contractor agreed to construct a 12 km road in 180 days for which he employed 120 men. After 80 days construction of only 4 km road was completed. How many additional men should he employ to complete the work as per the agreement?

Question

A contractor agreed to construct a 12 km road in 180 days for which he employed 120 men. After 80 days construction of only 4 km road was completed. How many additional men should he employ to complete the work as per the agreement?

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we need to find out how many additional men the contractor should employ to complete the remaining 8 km of the road within the agreed-upon 180 days.

First, let's calculate the rate at which the contractor and his current team are constructing the road. In 80 days, they were able to complete 4 km of the road. Therefore, their rate of construction is 4 km / 80 days = 0.05 km/day.

Now, let's calculate how many days it would take for the contractor and his current team to complete the remaining 8 km of the road. We can use the rate of construction we just calculated:

Time = Distance / Rate Time = 8 km / 0.05 km/day Time = 160 days

Since the contractor has already used up 80 days, he has 180 - 80 = 100 days left to complete the remaining 8 km of the road.

To find out how many additional men the contractor should employ, we can set up a proportion:

120 men / 80 days = X men / 100 days

Cross-multiplying, we get:

120 men * 100 days = 80 days * X men 12,000 men-days = 80X men-days

Dividing both sides by 80, we find:

12,000 men-days / 80 = X men 150 men = X men

Therefore, the contractor should employ an additional 150 men to complete the work as per the agreement.

This problem has been solved

Similar Questions

45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work

12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required? 60 74 68 70

Eighteen workers can lay a road in 24 days working 12 hours a day.  In how many days can 54 workers lay a road which has one-third more length than the earlier one, working 8 hours a day?

4 men can repair a road in 7 hours. How many men are required to repair the road in 2 hours?

45 men complete a piece of work in 30 days working 12 hours a day. In how many days will 60 men complete the work if working 10 hours a day

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.