The number of days needed in repairing a house varies inversely as the number of men working. It takes 15 days for 2 men to repair the house. How many men are needed to complete the job in 6 days?

Question

The number of days needed in repairing a house varies inversely as the number of men working. It takes 15 days for 2 men to repair the house. How many men are needed to complete the job in 6 days?

🧐 Not the exact question you are looking for?Go ask a question

Solution

Let's solve this problem step by step:

Step 1: Identify the given information:

  • It takes 15 days for 2 men to repair the house.

Step 2: Set up the inverse variation equation: Let d be the number of days needed to repair the house, and let m be the number of men working. According to the problem, the number of days needed varies inversely with the number of men working. Therefore, we can write the equation as: d = k/m, where k is the constant of variation.

Step 3: Find the value of k: To find the value of k, we can use the given information. We know that it takes 15 days for 2 men to repair the house. Substituting these values into the equation, we get: 15 = k/2 Solving for k, we multiply both sides by 2: k = 30

Step 4: Use the equation to find the number of men needed to complete the job in 6 days: We want to find the number of men needed to complete the job in 6 days. Let's call this number x. Substituting the values into the equation, we get: 6 = 30/x Solving for x, we multiply both sides by x: 6x = 30 Dividing both sides by 6, we get: x = 5

Therefore, 5 men are needed to complete the job in 6 days.

This problem has been solved

Similar Questions

A man can do a job in 15 days. If he works for 5 days and then leaves, how many days will it take for 3 men to complete the remaining work?A) 5 daysB) 6 daysC) 7 daysD) 8 days

10 men and 15 women together can complete a work in 6 days. It takes 100 days for one man alone to complete the same work. How many days will be required for one woman alone to complete the same work

When building a house, the number of days required to build varies inversely with the number of workers. One house was built in 119 days by 3 workers. How many days would it take to build a similar house with 17 workers?

Select the correct answerIf 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, then the time taken by 15 men and 20 boys to do the same type of work will be?Options5 days6 days7 days4 days

A group of men can do a work in certain number of days. After having worked for 18 days, of them leave. To complete the remaining work, the remaining men take the same number of days as the initial number of men would have taken to complete the entire work. In how many days is the entire work done?

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.