The earliest finish time for an activity is equal to the latest finish time minus the activity slack.Group startsTrue or False

Question

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.Group startsTrue or False

🧐 Not the exact question you are looking for?Go ask a question

Solution

False. The earliest finish time for an activity is calculated by adding the activity's duration to its earliest start time. The activity slack, or float, is the amount of time that you can delay a task without delaying the project. More slack time means that project scheduling is more flexible.

Similar Questions

The earliest possible time an activity can start is known as:a.Early Start timeb.Early finish timec.Activitiesd.Cost

The higher the node number, the longer the activity will take.Group startsTrue or False

For an activity in a CPM analysis, the early finish time is 12 and the late finish time is 12. Which of the following statements is true? Group of answer choicesThe duration of this activity is 12.The late start is 12.The early start is 12.The activity could be on the critical path.The slack for this activity is 12.

The early start of an activity that has only one predecessor is equal to the early finish of that predecessor.Group of answer choicesTrueFalse

In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse