The higher the node number, the longer the activity will take.Group startsTrue or False
Question
The higher the node number, the longer the activity will take.Group startsTrue or False
Solution
False. The node number in a project management context, often used in techniques like the Critical Path Method (CPM), does not determine the duration of an activity. The node number is just a way to identify and organize the activities. The duration of each activity is determined by factors like the complexity of the task, resources available, etc., not by the node number.
Similar Questions
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.Group startsTrue or False
The sequence of activity in network diagrams is shown by?a.Arrowsb.Nodesc.Circlesd.squares
Represents the amount of time an activity can be delayed without impacting the critical path or project completion.a.Slackb.Nodesc.Activitiesd.Duration
The early start of an activity that has only one predecessor is equal to the early finish of that predecessor.Group of answer choicesTrueFalse
Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 isGroup of answer choices8752