For an activity in a CPM analysis, the early finish time is 12 and the late finish time is 12. Which of the following statements is true? Group of answer choicesThe duration of this activity is 12.The late start is 12.The early start is 12.The activity could be on the critical path.The slack for this activity is 12.
Question
For an activity in a CPM analysis, the early finish time is 12 and the late finish time is 12. Which of the following statements is true? Group of answer choicesThe duration of this activity is 12.The late start is 12.The early start is 12.The activity could be on the critical path.The slack for this activity is 12.
Solution
The activity could be on the critical path.
In a Critical Path Method (CPM) analysis, if the early finish time and the late finish time for an activity are the same, it suggests that the activity could be on the critical path. The critical path is the sequence of activities with zero slack, meaning they cannot be delayed without delaying the project. Therefore, if an activity has the same early and late finish times, it has zero slack and could be on the critical path.
Similar Questions
In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse
What is true about the PERT/CPM technique for creating a suitable schedule for the given project1. It is based on the work breakdown structure.2. The early start and Early finish times are obtained while calculating backwords.3. Slack time for a task not falling in the critical path cannot be zero.4. Slack time for all tasks falling in the critical path must be zero.5. The late finish of the project is the same time with which the last task finishes at the earliest possible time.Group of answer choices1, 2, and 41 and 31, 3, and 53 and 5
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.Group startsTrue or False
A(n) _____ determines the early start and early finish dates for each activity in a project.
Given the CPM/PERT project network segment the latest finish (LF) times for activity 3 isGroup of answer choices8752
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.