Choose the correct option from those given below.If a process can ideally be completed in 13 days, what would you infer if the cycle time of the same process was marked as 15 days? The process is highly efficientThe process is highly inefficientInformation is inadequate

Question

Choose the correct option from those given below.If a process can ideally be completed in 13 days, what would you infer if the cycle time of the same process was marked as 15 days? The process is highly efficientThe process is highly inefficientInformation is inadequate

🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct option would be "The process is highly inefficient". This is because if a process can ideally be completed in 13 days but is actually taking 15 days, it means it's taking longer than it should, indicating inefficiency.

Similar Questions

Select the correct answerA can complete a work in 12 days, B in 15 days. Find the time taken by them: If A leaves two days before the scheduled completion of the work.Options9 4/79 1/69 5/69 2/3

If A is 25% as efficient as B and can complete a certain work taking 15 days more than the time taken by B, in how many days will both A and B together complete the work?4 days5 days7 days10 days

Select the correct answerA can complete a work in 12 days, B in 15 days. When A and B worked alternatively, when started byOptions13 2/5 days12 2/5 days11 2/5 days13 3/5 days

Select the correct answerA can do a certain work in 12 days. B is 60% more efficient than A. How many days will B and A together take to do the same job?Options80/13 days75/13 days60/13 days70/13 days

Select the correct answerA can complete a work in 12 days, B in 15 days. Find the time taken by them. When A and B working together.Options6 1/36 2/35 2/35 1/3Finish ClearPrev Next

1/3