Select the correct answerA can do a certain work in 12 days. B is 60% more efficient than A. How many days will B and A together take to do the same job?Options80/13 days75/13 days60/13 days70/13 days
Question
Select the correct answerA can do a certain work in 12 days. B is 60% more efficient than A. How many days will B and A together take to do the same job?Options80/13 days75/13 days60/13 days70/13 days
Solution
Sure, let's solve this step by step:
-
A can do a certain work in 12 days. This means the rate of A is 1/12 work per day.
-
B is 60% more efficient than A. This means B can do 1.6 times the work A does in a day. So, the rate of B is 1.6/12 = 0.1333 work per day.
-
To find out how many days A and B together will take to do the same job, we need to add their rates of work and then divide 1 (the whole work) by the sum of their rates.
-
The rate of A and B together is 1/12 + 0.1333 = 0.2167 work per day.
-
Therefore, A and B together will take 1/0.2167 = 4.6154 days to do the same job.
However, none of the options match this result. There might be a mistake in the problem or the options.
Similar Questions
Select the correct answerA takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is?Options27 days30 days20 days25 days
Select the correct answerA can complete a work in 12 days, B in 15 days. When A and B worked alternatively, when started byOptions12 1/4days14 1/4days12 3/4days13 1/4days
Select the correct answerA can complete a work in 12 days, B in 15 days. Find the time taken by them. When A and B working together.Options6 1/36 2/35 2/35 1/3
Select the correct answerA and B together can do a piece of work in 12 days which B and C together do in 16 days. If A works for 5 days, B works for 7 days than C completes the remaining work in 13 days. In how much time B alone does the whole work?Options48 days16 days24 days12 days
Select the correct answerA can do a work in 36 days and B in 32 days. If they work on it together for 12 days, then what fraction of work is left?Options7/24134557/7211933
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.