Knowee
Questions
Features
Study Tools

Select the correct answerA takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is?Options27 days30 days20 days25 days

Question

Select the correct answerA takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is?Options27 days30 days20 days25 days

🧐 Not the exact question you are looking for?Go ask a question

Solution

Let's solve this step by step:

  1. A and B together can finish the work in 12 days. So, their combined rate of work is 1/12 of the work per day.

  2. According to the problem, A takes 10 days less than B to finish the work. Let's say B takes 'x' days to finish the work. Then A takes 'x-10' days to finish the work.

  3. The rate of work of A is 1/(x-10) and the rate of work of B is 1/x.

  4. Since they can together finish the work in 12 days, their combined rate of work is the sum of their individual rates of work. So, we have the equation:

    1/(x-10) + 1/x = 1/12

  5. Solving this equation for 'x' will give us the time taken by B alone to finish the work.

  6. Multiply the entire equation by 12x(x-10) to clear the denominators:

    12x + 12(x-10) = x(x-10)

  7. Simplify the equation:

    12x + 12x - 120 = x^2 - 10x

  8. Rearrange the terms:

    x^2 - 34x + 120 = 0

  9. This is a quadratic equation in the form ax^2 + bx + c = 0. Solve for 'x' using the quadratic formula x = [-b ± sqrt(b^2 - 4ac)] / 2a:

    x = [34 ± sqrt((34)^2 - 41120)] / 2*1 x = [34 ± sqrt(1156 - 480)] / 2 x = [34 ± sqrt(676)] / 2 x = [34 ± 26] / 2

  10. We get two solutions: x = 30 and x = 4. But x cannot be 4 because then A would take 'x-10' = -6 days, which is not possible.

So, the time taken by B alone to finish the work is 30 days. Therefore, the correct answer is "30 days".

This problem has been solved

Similar Questions

Select the correct answerA can complete a work in 12 days, B in 15 days. Find the time taken by them: If A leaves two days before the scheduled completion of the work.Options9 4/79 1/69 5/69 2/3

Select the correct answerA and B together can do a piece of work in 12 days which B and C together do in 16 days. If A works for 5 days, B works for 7 days than C completes the remaining work in 13 days. In how much time B alone does the whole work?Options48 days16 days24 days12 days

Select the correct answerA can do a certain work in 12 days. B is 60% more efficient than A. How many days will B and A together take to do the same job?Options80/13 days75/13 days60/13 days70/13 days

Select the correct answerA can complete a work in 12 days, B in 15 days. When A and B worked alternatively, when started byOptions12 2/5 days11 2/5 days13 3/5 days13 2/5 days

Select the correct answerA and B together can finish a work in 6.75 days. A alone can finish the same work in 9 days. In how many days will B alone finish the work?Options27 days18 days35 days36 days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.