Select the correct answerA takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is?Options27 days30 days20 days25 days
Question
Select the correct answerA takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is?Options27 days30 days20 days25 days
Solution
Let's solve this step by step:
-
A and B together can finish the work in 12 days. So, their combined rate of work is 1/12 of the work per day.
-
According to the problem, A takes 10 days less than B to finish the work. Let's say B takes 'x' days to finish the work. Then A takes 'x-10' days to finish the work.
-
The rate of work of A is 1/(x-10) and the rate of work of B is 1/x.
-
Since they can together finish the work in 12 days, their combined rate of work is the sum of their individual rates of work. So, we have the equation:
1/(x-10) + 1/x = 1/12
-
Solving this equation for 'x' will give us the time taken by B alone to finish the work.
-
Multiply the entire equation by 12x(x-10) to clear the denominators:
12x + 12(x-10) = x(x-10)
-
Simplify the equation:
12x + 12x - 120 = x^2 - 10x
-
Rearrange the terms:
x^2 - 34x + 120 = 0
-
This is a quadratic equation in the form ax^2 + bx + c = 0. Solve for 'x' using the quadratic formula x = [-b ± sqrt(b^2 - 4ac)] / 2a:
x = [34 ± sqrt((34)^2 - 41120)] / 2*1 x = [34 ± sqrt(1156 - 480)] / 2 x = [34 ± sqrt(676)] / 2 x = [34 ± 26] / 2
-
We get two solutions: x = 30 and x = 4. But x cannot be 4 because then A would take 'x-10' = -6 days, which is not possible.
So, the time taken by B alone to finish the work is 30 days. Therefore, the correct answer is "30 days".
Similar Questions
Select the correct answerA can complete a work in 12 days, B in 15 days. Find the time taken by them: If A leaves two days before the scheduled completion of the work.Options9 4/79 1/69 5/69 2/3
Select the correct answerA and B together can do a piece of work in 12 days which B and C together do in 16 days. If A works for 5 days, B works for 7 days than C completes the remaining work in 13 days. In how much time B alone does the whole work?Options48 days16 days24 days12 days
Select the correct answerA can do a certain work in 12 days. B is 60% more efficient than A. How many days will B and A together take to do the same job?Options80/13 days75/13 days60/13 days70/13 days
Select the correct answerA can complete a work in 12 days, B in 15 days. When A and B worked alternatively, when started byOptions12 2/5 days11 2/5 days13 3/5 days13 2/5 days
Select the correct answerA and B together can finish a work in 6.75 days. A alone can finish the same work in 9 days. In how many days will B alone finish the work?Options27 days18 days35 days36 days
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.