Select the correct answerA can complete a work in 12 days, B in 15 days. When A and B worked alternatively, when started byOptions13 2/5 days12 2/5 days11 2/5 days13 3/5 days
Question
Select the correct answerA can complete a work in 12 days, B in 15 days. When A and B worked alternatively, when started byOptions13 2/5 days12 2/5 days11 2/5 days13 3/5 days
Solution
To solve this problem, we first need to find out how much work A and B can do in one day.
- A can complete the work in 12 days, so A can do 1/12 of the work in one day.
- B can complete the work in 15 days, so B can do 1/15 of the work in one day.
When A and B work alternatively, they can complete (1/12 + 1/15) of the work in two days.
To simplify this, we find the least common multiple of 12 and 15, which is 60. So, A can do 5/60 of the work in one day and B can do 4/60 of the work in one day.
Therefore, in two days, A and B can complete (5/60 + 4/60) * 2 = 18/60 = 3/10 of the work.
To find out how many two-day periods it takes for A and B to complete the work, we divide the total work (1) by the work they can do in two days (3/10), which gives us 10/3 ≈ 3.33 two-day periods.
Since each two-day period is actually two days, we multiply 3.33 by 2 to find out how many days it takes for A and B to complete the work, which gives us 6.67 days.
However, since A and B work alternatively and A starts the work, A will work on the first day, B on the second day, A on the third day, B on the fourth day, A on the fifth day, B on the sixth day, and A will need to work on the seventh day to complete the work.
So, the correct answer is 6 full days and 2/5 of the seventh day, which is 6 2/5 days. But this option is not available in the given options.
Therefore, there seems to be a mistake in the question or the options provided.
Similar Questions
Select the correct answerA can complete a work in 12 days, B in 15 days. Find the time taken by them: If A leaves two days before the scheduled completion of the work.Options9 4/79 1/69 5/69 2/3
Select the correct answerA can complete a work in 12 days, B in 15 days. Find the time taken by them. When A and B working together.Options6 1/36 2/35 2/35 1/3Finish ClearPrev Next
Select the correct answerA takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is?Options27 days30 days20 days25 days
Select the correct answerA can do a certain work in 12 days. B is 60% more efficient than A. How many days will B and A together take to do the same job?Options80/13 days75/13 days60/13 days70/13 days
Select the correct answerA, B, C can do a work in 5 days, 10 days and 15 days respectively. They started together to do the work but after 2 days A and B left. C did the remaining work in how many days?Options3 days4 days3 1/2days2 days
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.