When they work alone, B needs 60% more time to finish a piece of work than A does. Both of them finish the work in the following manner: B works alone till one-fourth of the work is done, then A and B work together for 12 days, and finally, A works alone to complete the remaining 10% of the work. In how many days can A alone finish the entire work?
Question
When they work alone, B needs 60% more time to finish a piece of work than A does. Both of them finish the work in the following manner: B works alone till one-fourth of the work is done, then A and B work together for 12 days, and finally, A works alone to complete the remaining 10% of the work. In how many days can A alone finish the entire work?
Solution
Let's denote the time A needs to finish the work alone as 'a' days.
Since B needs 60% more time to finish the work than A does, B would need 1.6a days to finish the work alone.
We know that work done is inversely proportional to time taken. So, the work done by A in one day is 1/a and the work done by B in one day is 1/(1.6a).
According to the problem, B works alone till one-fourth of the work is done. So, B works for (1/4)*(1.6a) = 0.4a days.
Then, A and B work together for 12 days. The work done by A and B in one day is 1/a + 1/(1.6a). So, the work done by A and B in 12 days is 12*(1/a + 1/(1.6a)).
Finally, A works alone to complete the remaining 10% of the work. So, A works for (1/10)*a = 0.1a days.
Adding up all these times, we get the total time taken to finish the work as 0.4a + 12 + 0.1a = 0.5a + 12.
But we know that the total time taken to finish the work should be 'a' days. So, we can set up the equation 0.5a + 12 = a and solve for 'a'.
Subtracting 0.5a from both sides, we get 12 = 0.5a.
Dividing both sides by 0.5, we get a = 24.
So, A alone can finish the entire work in 24 days.
Similar Questions
A can do 2/5 of a work in 12 days while B can do 66 2/3% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in?Options6498
A can do work in 20 days. Then, he is assisted by B to complete the remaining work in 12 days. In how much time can B alone do the work?
A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is?Options30 days20 days25 days27 days
A and B together can complete a piece of work in 35 days, while A alone can complete it in 60 days. So, B alone can complete the work in how many days?
A and B together can do a piece of work in 8 days, but A alone can do it in 12 days. How manydays would B alone take to do the same work?
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.