A can do 2/5 of a work in 12 days while B can do 66 2/3% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in?Options6498

Question

A can do 2/5 of a work in 12 days while B can do 66 2/3% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in?Options6498

🧐 Not the exact question you are looking for?Go ask a question

Solution

Sure, let's solve this step by step:

  1. First, let's find out how much work A and B can do in one day.

    A can do 2/5 of the work in 12 days, so in one day, A can do (2/5)/12 = 1/30 of the work.

    B can do 66 2/3% of the work in 16 days. 66 2/3% is equivalent to 2/3 in fraction. So, in one day, B can do (2/3)/16 = 1/24 of the work.

  2. Now, let's find out how much work they can do together in one day.

    A and B together can do 1/30 + 1/24 = 4/120 + 5/120 = 9/120 = 3/40 of the work in one day.

  3. They work together for 10 days, so in 10 days, they can do 10 * 3/40 = 3/4 of the work.

  4. The remaining work is 1 - 3/4 = 1/4.

  5. Now, let's find out how many days B will take to complete the remaining work.

    Since B can do 1/24 of the work in one day, B will take 1/4 / 1/24 = 24/4 = 6 days to complete the remaining work.

So, B alone will complete the remaining work in 6 days. The correct option is 6.

This problem has been solved

Similar Questions

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

A can do a work in 36 days and B in 32 days. If they work on it together for 12 days, then what fraction of work is left?Options7/2411933134557/72

A can finish one-third of a work in 5 days, B can finish 2/5th of the same work in 10 days and C can finish 75% of the same work in 15 days. They work together for 6 days; The remaining work will be finished by B alone in?Options5 days3 days2.5 days1.5 days

A and B can complete a work in 6 days.A can alone do it in 10 days.Then B can alone do the work in how many days?A13.75 daysB14 daysC16 daysD15 days

When they work alone, B needs 60% more time to finish a piece of work than A does. Both of them finish the work in the following manner: B works alone till one-fourth of the work is done, then A and B work together for 12 days, and finally, A works alone to complete the remaining 10% of the work. In how many days can A alone finish the entire work?

1/3