A can do work in 20 days. Then, he is assisted by B to complete the remaining work in 12 days. In how much time can B alone do the work?
Question
A can do work in 20 days. Then, he is assisted by B to complete the remaining work in 12 days. In how much time can B alone do the work?
Solution
Let's solve the problem step by step:
-
Let's assume that the total work to be done is represented by the variable "W".
-
We are given that A can complete the work in 20 days. Therefore, A's work rate can be calculated as 1/20 of the total work per day.
-
A and B together complete the remaining work in 12 days. This means that in 12 days, they complete 1 - 1/20 = 19/20 of the total work.
-
Let's represent B's work rate as "x" (in terms of the total work per day). Since A and B together complete 19/20 of the work in 12 days, we can set up the equation: (1/20 + x) * 12 = 19/20.
-
Simplifying the equation, we get: 12/20 + 12x = 19/20.
-
Multiplying both sides of the equation by 20 to eliminate the fractions, we get: 12 + 240x = 19.
-
Rearranging the equation, we get: 240x = 19 - 12.
-
Simplifying further, we get: 240x = 7.
-
Dividing both sides of the equation by 240, we get: x = 7/240.
-
Therefore, B's work rate is 7/240 of the total work per day.
-
To find out how much time B alone can do the work, we need to calculate the reciprocal of B's work rate. So, B can complete the work in 240/7 days.
-
Simplifying the fraction, we get: B can complete the work in approximately 34.29 days.
Therefore, B alone can do the work in approximately 34.29 days.
Similar Questions
A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is?Options30 days20 days25 days27 days
A and B together can do a piece of work in 8 days, but A alone can do it in 12 days. How manydays would B alone take to do the same work?
When they work alone, B needs 60% more time to finish a piece of work than A does. Both of them finish the work in the following manner: B works alone till one-fourth of the work is done, then A and B work together for 12 days, and finally, A works alone to complete the remaining 10% of the work. In how many days can A alone finish the entire work?
A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work on alternate days. The total work will be completed in ______.
A can do a work in 15 days and B in 20 days. In how many days will they work together to finish the work
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.