A wall is built by 17 men in 24 days. In how many days can 18 men do the work if hours per day is reduced in the ratio 5:4? radio_button_unchecked 29.75 days radio_button_unchecked 28.33 days radio_button_unchecked 30.33 days radio_button_unchecked 35.25 days

Question

A wall is built by 17 men in 24 days. In how many days can 18 men do the work if hours per day is reduced in the ratio 5:4?

radio_button_unchecked 29.75 days

radio_button_unchecked 28.33 days

radio_button_unchecked 30.33 days

radio_button_unchecked 35.25 days

🧐 Not the exact question you are looking for?Go ask a question

Solution

First, we need to understand that the time taken to complete a work is inversely proportional to the number of men working and directly proportional to the number of hours worked.

Given that 17 men can build a wall in 24 days, we can say that the work done is equivalent to 17 men * 24 days = 408 man-days.

Now, we are asked to find out how many days it would take for 18 men to do the same work if the hours per day is reduced in the ratio 5:4. This means that they are now working 4/5th of the time they were previously working.

So, the time taken by 18 men to do the same work would be (408 man-days) / (18 men * 4/5) = 28.33 days.

Therefore, the correct answer is:

radio_button_unchecked 29.75 days

radio_button_checked 28.33 days

radio_button_unchecked 30.33 days

radio_button_unchecked 35.25 days

This problem has been solved

Similar Questions

If 10 men can do a work in 4 days, in how many days can 8 men do it? radio_button_unchecked 7 days radio_button_unchecked 5 days radio_button_unchecked 8 days radio_button_unchecked 6 days

Sixteen men can complete a work in 22 days working 12 hours a day.  In how many days can 24 men complete the same work working 16 hours a day?

Select the correct answerTo complete a tender in 30 days, 30 men are employed. When the work was reviewed after 20 days, only half of the work was completed. To complete the tender in the estimated time find the number of men to be working in the remaining days.radio_button_unchecked30radio_button_unchecked60radio_button_unchecked90radio_button_unchecked45

A, B and C can do a piece of work in 12, 24 and 48 days respectively. In how many days A can do the work if he is assisted by B and C on every fourth day?radio_button_unchecked9 daysradio_button_unchecked10.5 daysradio_button_unchecked11.5 daysradio_button_unchecked12 days

20 men can complete a task in 30 days. If one man leaves the site at the end of each day, then what fraction of work will be completed?

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.