Knowee
Questions
Features
Study Tools

20 men can complete a task in 30 days. If one man leaves the site at the end of each day, then what fraction of work will be completed?

Question

20 men can complete a task in 30 days. If one man leaves the site at the end of each day, then what fraction of work will be completed?

🧐 Not the exact question you are looking for?Go ask a question

Solution

To find the fraction of work completed, we need to determine how many men are left on the site each day.

Initially, there are 20 men on the site, and they can complete the task in 30 days. This means that each man contributes 1/20th of the work per day.

On the first day, all 20 men are present, so they complete 20/20 or 1 whole unit of work.

On the second day, one man leaves, so there are 19 men remaining. Each man still contributes 1/20th of the work, so they complete 19/20th of the remaining work.

On the third day, another man leaves, leaving 18 men. They complete 18/20th of the remaining work.

This pattern continues until the 30th day, where only one man is left and he completes 1/20th of the remaining work.

To find the total fraction of work completed, we add up all the fractions from each day.

1/20 + 19/20 + 18/20 + ... + 1/20

This can be simplified to:

(1 + 19 + 18 + ... + 1) / 20

To find the sum of the numbers from 1 to 20, we can use the formula for the sum of an arithmetic series:

Sum = (n/2)(first term + last term)

In this case, the first term is 1, the last term is 20, and the number of terms is 20.

Sum = (20/2)(1 + 20) = 10(21) = 210

So the total fraction of work completed is:

210/20 = 21/2

Therefore, the fraction of work completed when one man leaves the site at the end of each day is 21/2.

This problem has been solved

Similar Questions

45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work

45 men complete a piece of work in 30 days working 12 hours a day. In how many days will 60 men complete the work if working 10 hours a day

A certain task can be completed in 60 mandays. How many men are required to complete 23 of thistask within 5 days?

If 3 men and 4 women can finish the work in 24 days, 4 men and 8 women can finish the same work in 15 days, in how many days will it take for one man alone to finish the same work?

A group of men can do a work in certain number of days. After having worked for 18 days, of them leave. To complete the remaining work, the remaining men take the same number of days as the initial number of men would have taken to complete the entire work. In how many days is the entire work done?

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.