Question 1You create a work breakdown structure. One of the major milestones is securing a venue for a conference. There are smaller jobs that must be done to reach each milestone. What are the smaller jobs known as?1 pointDeliverablesRoles and responsibilitiesChecklist itemsTasks and sub-tasks

Question

Question 1You create a work breakdown structure. One of the major milestones is securing a venue for a conference. There are smaller jobs that must be done to reach each milestone. What are the smaller jobs known as?1 pointDeliverablesRoles and responsibilitiesChecklist itemsTasks and sub-tasks

🧐 Not the exact question you are looking for?Go ask a question

Solution

The smaller jobs that must be done to reach each milestone in a work breakdown structure are known as Tasks and sub-tasks.

Similar Questions

A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task? A list that identifies the logical way to progress through workTangible and measurable outcome expected from a projectWork performed to complete or manage the deliverables for a projectDiscrete work required to complete parts of a project

Which of the following elements is NOT included as part of the five-step process of developing a work breakdown structure?Developing the budgetIdentifying tasksIdentifying deliverablesSequencing the activities

. Which of the following statements describes the relationship among tasks, stages, and jobs? A task is another name for a job. A stage can contain either tasks or jobs.Stages break down into jobs, and jobs break down into tasks.Stages break down into tasks. A job schedules when each stage runs.

Apa yang dimaksud dengan WBS (Work Breakdown Structure)?Question 34Answera.Work Breakdown Scheduleb.World Business Systemc.Work Breakdown Structured.Work Budgeting System

Job specialization involves Blank______.Multiple choice question.dividing tasks into smaller jobssetting up departments to do specialized tasksincreasing the tasks given employeesrotating employees into different jobs