Multiple Choice QuestionSpring Company uses activity-based costing to allocate their overhead costs. Setup costs of $100,000 are based on number of setups. Factory services of $65,000 are based on square footage. Spring Company has identified 500 setups and has 10,000 square feet in their factory. What is the activity rate for the setup activity cost pool.Multiple choice question.$330.00$16.50$6.50$200.00
Question
Multiple Choice QuestionSpring Company uses activity-based costing to allocate their overhead costs. Setup costs of 65,000 are based on square footage. Spring Company has identified 500 setups and has 10,000 square feet in their factory. What is the activity rate for the setup activity cost pool.Multiple choice question.16.50200.00
Solution
To calculate the activity rate for the setup activity cost pool, you need to divide the total setup costs by the number of setups.
Here's the step-by-step calculation:
- Identify the total setup costs: $100,000
- Identify the number of setups: 500
- Divide the total setup costs by the number of setups: 200
So, the activity rate for the setup activity cost pool is $200.00.
Similar Questions
Multiple Choice QuestionJackson Company uses activity-based costing to allocate their overhead costs. Setup costs of $850,000 are based on number of batches. Design modification costs of $155,000 are based on number of design changes. Jackson Company has identified 40,000 batches and has 5,000 design changes in their factory. What is the activity rate for setup.Multiple choice question.$3.88$21.25$25.13$31.00
Multiple Choice QuestionJohnson Company has the following overhead costs: machine setup $25,000; factory services $10,000; design of $15,000; and selling expenses of $5,000. What is the total overhead costs using activity-based costing?Multiple choice question.$50,000.$40,000.$20,000.$55,000.
Fill in the Blank QuestionFill in the blank question.A company has the following activities and costs: machine setup of $5,000 per setup and factory services of $100 per square foot. If product 1 uses 2 setups and has 10,000 square feet, overhead allocated to product 1 is $.
Given the following information, assign overhead costs to Product B using ABC. ActivityCostsCost DriverAssembling costs$200,000Machine-hoursSetup costs$75,000Number of setupsInspecting costs$50,000Direct labor-hours ActivityProduct A UseProduct B UseAssembling costs500 machine-hours300 machine-hoursSetup costs10 setups15 setupsInspecting costs25 direct labor-hours15 direct labor-hoursMultiple choice question.$138,750$125,250$150,750
Given the following information, compute the cost driver rate for assembling costs. ActivityCostsCost DriverAssembling costs$200,000Machine-hoursSetup costs$75,000Number of setupsInspecting costs$50,000Direct labor-hours ActivityProduct A UseProduct B UseAssembling costs500 machine-hours300 machine-hoursSetup costs10 setups15 setupsInspecting costs25 direct labor-hours15 direct labor-hoursMultiple choice question.$400 per machine-hour$133 per machine-hour$250 per machine-hour$667 per machine-hour
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.